Power Flow Optimization with Energy Storage - Sal Island Case Study
DENIS SANTOS1,2, VASCO SANTOS2,3
1Claranet - Digital Competence Center,
Polytechnic Institute of Viseu,
Campus Politécnico, 3504-510 Viseu,
PORTUGAL
2Electrical Engineering Department,
Polytechnic Institute of Viseu,
Campus Politécnico, 3504-510 Viseu,
PORTUGAL
3CISeD – Research Centre in Digital Services,
Polytechnic Institute of Viseu,
Campus Politécnico, 3504-510 Viseu,
PORTUGAL
Abstract: - The correlation between energy costs and the country's economic competitiveness is an
unquestionable reality also responsible for the improvement of the population's life conditions. In the past Cape
Verdean electric power system (EPS), expansion was based on fossil-fuel power plants, nowadays it shifted to
renewable energy (RE) which is abundant in the Cape Verde archipelago. However, no reduction in the
electricity tariffs occurred, due to renewable curtailment and other pendent questions related to power
transmission losses in the EPS.
This paper presents an approach, that supports an implementation of a distributed electric energy storage
system (ESS) on the Sal Island of Cape Verde archipelago, as a solution to increase the RE integration and
power Transmission congestion relief. Thus, a power flow optimization is only achievable by storing excess RE
as near as possible to consumption buses that can reduce overall transmission losses. The most advantageous
allocation of ESSs along the EPS buses is combinational which faces a maximization of transmission loss
reduction and minimization of ESS investment capital. The proposed tool to manage the “trade-off” between
cost and avoided losses, is based on a genetic algorithm (GA) that is broadly applied to multi-objective
problems like this.
Key-Words: - Distributed Generation, Power Flow, Renewable Energy, Curtailment, Genetic Algorithms,
Energy Storage.
Received: September 12, 2022. Revised: September 2, 2023. Accepted: Ocotber 7, 2023. Published: November 8, 2023.
1 Introduction
The EPS of Sal Island is this paper’s case study
object because it is one of the most expanding
energy systems in the archipelago which also was
followed by a growth of power transmission losses.
Furthermore, a large portion of wind energy
available in the island’s Wind Power Plant is
curtailed since the peak consumption that usually
doesn’t match with the existing Wind Power Plant
peak production, which is unfeasible because the
Diesel Power Plant minimum production must
represent at least 50% of the production mix to
ensure grid stability and spinning reserve.
Electricity production costs on the island depended
on the fossil fuel importation costs, which had led to
high susceptibility and dependence on international
events. After an increase of 30% in energy costs
from 2005 to 2009, following Brent’s increasing
price, the government initiated a baseline plan for
RE in Cape Verde, to obtain Sustainable Energy
from an economic and environmental point of view.
To solve this situation a Solar Power Plant and
Wind Power Plant were installed on the island and
began operating, increasing endogenous production
as defined in a document titled Plano de Energias
Renováveis de Cabo Verde-2011”, [1].
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
216
Volume 18, 2023
When the RE power plants started operating Sal´s
EPS began to have some stability problems and
couldn’t absorb all ER produced, which is why
curtailment started to assume values above 40%,
that’s why this papers case study is focused on the
use of ESS to improve RE integration. At the same
periods of consumption present in the load diagram,
ESS helps reduce power flow between generation
buses and load buses, by providing energy
discharging next to the consumption distribution
buses.
Some advantages of the ESS implementation on the
island are not accounted in this paper, which is
stated as follows:
Electrical network Investment Deferral (Cables
and transformers);
Better use of land disposable to RE plant´s
operation;
Improving RE plants life cycle and producing
energy.
Typically the companies responsible for the sizing
and location of ESS on the grid, do not take into
account reduction in power losses, they usually
locate da ESS nearby the RE source (Wind Power
Plants or Solar Power Plants) or near consumption
as an efficient way of storing energy, but some
researchers look to the grid as an all, trying to
allocate the best size ESS units that guarantee
technical and economic stability of the grid. As
examples we can see the following two articles:
The authors in, [2], have shown that a multi-
objective multiverse optimization method
(MOMVO) is used as a solution tool for optimal
allocation and sizing of ESS in Power Grids to
improve the voltage profiles and minimize the
annual costs, as result a Pareto optimal solution set
is minimized under economic concerns and cost
sensitivity to provide a decision-support for the
utilities. In, [3], is proposed a three multi-objective
algorithms of particle swarm optimization (PSO),
variable constants (VCPSO) and genetic algorithm
(GA), the main objectives of this solution tool are to
detect the optimum size and location of multiple
ESS aiming to reduce active power loss and
improve bus voltage deviations in the distribution
networks.
In this context, this paper presents an approach,
that supports an implementation of a distributed
electric energy storage system (ESS) on the Sal
Island of Cape Verde archipelago, as a solution to
increase the RE integration and power transmission
congestion relief. Thus, a power flow optimization
is only achievable by storing excess RE as near as
possible to consumption buses that can reduce
overall transmission losses. The most advantageous
allocation of ESSs, and selecting their best size
capacity along the EPS buses is combinational
which faces a maximization of achieved
transmission loss reduction and minimization of
ESS investment capital. The mathematical model
herein proposed involves both discrete and
continuous variables as well as nonlinear
constraints, namely related to power flow equations.
Therefore, due to the presence of multiple objective
functions, non-linear relations, and its combinatorial
nature the model is hard to solve using mathematical
programming algorithms. This was the motivation
to resort to GAs to compute non-dominated
solutions to the model developed, [4], [5].
2 Sal Island EPS Characterization
Sal Island is located on the Northeast of the
archipelago, with a total area of 220km2. There is
approximately 30.000 inhabitants, distributed along
the four places (Espargos - main local residential
and administrative city, Santa Maria - touristic
center, Palmeira - port and fishing town, Pedra
Lume -fishing village). The electricity needs of Sal
Island is approximately 72GWh per year. This
amount of electricity is provided in 67,4% by the
Diesel Power Plant of Palmeira town and
Wind/Solar Power Plants that represent 27% and
5,6% of the energetic matrix respectively), [6].
Electra a state owned company is the EPS
concessionary, that operates Palmeira´s Diesel
Power Plant whit 12MW of installed power capacity
to provide energy security and required a spinning
reserve to absorb RE intermittency. The
concessionary also operates a Wind Power Plant
with an installed capacity of 3x1,6MW. As
concluded in a RE assessment, it was strategic to
construct a 2,5MW Solar Power Plant on Sal Island
in a strategic place reserved by law as a Renewable
Energy Development Zone (ZDER), [1], [7].
Electra follows energy sector directives defined
by the local State Agency for Energy, which
currently encourages the entry of private initiative
on the EPS, while seeking to solve Electra´s poor
financial performance, caused by elevated technical
and commercial losses and slow technologic
transition influenced by fuel oil (180 to 380 heavy
fuel) volatile prices.
The electricity price is regulated by the
Economic Regulation Agency (ERA), which is
responsible for balancing the interests of consumers
and producers, [8], [9].
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
217
Volume 18, 2023
Fig. 1: Yearly wind availability and statistics on Sal
Island, 2018.
The Islands plan morphology concedes a low
spatial variance of wind availability, but still land-
use is environmentally concerning and restricted by
the aeronautic hub. As shown in Figure 1, wind
temporal availability is constant, having a small
seasonal sag from June to November, studies
suggest 2700 equivalent full load hours, [10]. The
highest wind availability is registered between 6PM-
7AM night-time period.
Sal Island´s Wind Power Plant is operated by
Caboéolica a company formed from a public-private
partnership. The energy is bought by Electra at a
cost of 0,14€/kWh in a “take or pay “signed
contract, [11].
Sal Island electricity consumption doesn´t vary
much over a year period, due to a diversification and
expanding tourist market activity, which is levelling
the Island’s energy consumption and due to a very
stable weather factor.
3 Overview of Storage Technologies
The main technologies to store electric energy are
based on converting it into a storable type of energy
(mechanical, thermal, electrochemical), so it can be
used later using a mechanism to reconvert it back on
electricity. The main characteristics that define the
best sights and strategies where a specific type of
ESS can be applied in EPS are: specific
power/energy, volume/density, charge/discharge
rate and life cycle, [8], [12], [13].
Mechanical storage like Reverse Pumping,
Flywheel or Compressed Air Energy Storage
(CAES), is based on converting electric energy into
gravity potential, rotational inertial or elastic
potential energy, respectively, [14]. CAES and
Reversed Pumping are more profitable on large
scale Power solutions where large quantities of
energy can be stored and used for a long period of
time, usually these technologies have geological and
geographic installation restrictions. Flywheels are
more intended for fast power response, commonly
used for energy quality, which is very useful for
stabilizing the start-up of RES.
Electricity can also be stored in an electrostatic
filed between two plates inside a double layer
capacitor (Super Capacitors) or in a magnetic field
in a cryogenically cooled super conducting coil
(SMES-Superconducting magnetic energy storage),
[15]. These two Electric storage technologies are
used in EPS when a huge amount of power is
needed in a very short time period, often used in
research facilities or to compensate large industrial
machinery voltage fluctuation caused by their
operation (ex: cranes, arc forge, etc.).
Thermal energy storage can be done in
cryogenics or heat which are typically associated to
three types of technologies depending on the heated
material, defined as: Sensible Heat, increases
temperature of a mass; Latent Heat, storage takes
advantage of the energy absorbed or released during
a phase change and thermochemical energy storage,
uses the heat absorption of a chemical reaction.
Practical applications of Cryogenics EES are
achieved by liquefying air or cooling water, [16].
Thermal ESS is usually cost-effective when
employed directly on HVAC or when energy is very
cheap like in electricity from nuclear Power Plants
or from RES surplus energy, [17].
Electricity is stored electrochemically in
Batteries whatever their chemistry (aqueous, no
aqueous, Li or Na-based) within the electrode
structure through charge transfer reactions
(oxidation-reduction), [18], [19]. In Other way, Fuel
Cells, store energy in the reactants that are
externally fed to the cells during the discharge
process, [20], [21]. Both of these differ from redox-
flow cells, which store energy in the redox species
that are circulating in a closed circuit through an
electrochemical cell, [20], [22].
Based on this description, different ESS can be
applied to the EPS to improve its operational
parameters caused by the variability of loads and
RES. So according to their characteristics some
technologies are used in:
Power quality - provides electrical service to
EPS during oscillations or disruptions to the
waveform such as swells/sags, spikes, or
harmonics;
Power bridge – ESS discharge in a short period
of time while the main source (thermic, hydro
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
218
Volume 18, 2023
or nuclear) is rising up or being set in grid
synchronization;
Energy Management - curtailed price of excess
energy produced at night can be used during
peak demand periods during the day time. This
allows arbitraging the production price of the
two periods and a more uniform/leveled load
factor as exemplified in Figure 2.
Fig. 2: Energy management is done by ESS; A)
peak shaving and B) load leveling.
The ESS technology most used in islands EPS
the size of Sal Island are ESS using lithium
batteries.
Some examples of this kind of implementations, are:
Canary archipelago - Grand Canary island,
1MW/3MW lithium-ion ESS, [23];
Azores archipelago Graciosa Island
7,4MWh/3,2MW lithium oxide titanium
ESS, [24].
In these examples typically to level a 2-hour
peak consumption the ESS size is suited in an
energy/power ratio of 2:1 and the charging is done
at night-time to avoid an increase on power flow
that results from the most abundant renewable
power excess period. Figure 3 presents an ESS
container topology based on lithium-ion batteries.
Fig. 3: Energy Storage System based on a container
string 9 strings 15 modules each, 700V 90Ah whit
63kWh.
Lithium battery ESS are used in these situations
because they have high reliability and low
maintenance and exploitation costs compared with
other batteries (Lead-Acid, NAS Flow, Zinc Air),
they have a bigger life cycle, specific power and
energy (including density), which makes them a
very interesting solution for island located
installations with low technologic Know-how.
4 Multi-objective Problem Optimization
The problem of finding the optimum location and
sizing ESS distributed along the EPS can be stated
as a multi-objective planning problem. In fact the
solution space is large, combinational, and nonlinear
where the fitness of each solution is analyzed to
guarantee that only strong solutions prevail, [25]. A
multi-objective method handles on a Pareto Front
(PF) display where it has the capability to give a
better understanding to the decision-makers (DM)
for selecting good compromise solutions having in
mind their economic and technical implementation.
The PF, in our case study, is a frontier in the
solution space where non-dominated solutions have
the best trade-off between investment cost and
avoided power losses.
Multi-objective problems (MOP) optimization
relies on three classes of methods: enumerative,
deterministic, and stochastic, [26]. The stochastic
methods such as GA have a great computational
performance and accessible implementation. It is a
bio-inspired method, also called an evolutionary
algorithm because its principles are based on
evolutionary theory like cross-over, mutation and
selection, which can be determinants of the survival
of the more fit individuals in the next generation.
Genetic Algorithms basic concepts
Gene - each variable in the solution is designated as
a gene usually coded in a binary, decimal, or grey;
for easier data manipulation, [27].
Chromosome - an array of genes that represents a
solution also designated as an individuum; the
position in the array identifies the variable, [28].
Non-dominance - a non-dominated solution is
defined as not having a solution with a better
performance to optimize the problem. As illustrated
in Figure 4.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
219
Volume 18, 2023
Fig. 4: Example of the dominance concept, used to
define an individuum’s fitness, on an AG
implementation, [29].
Populationis formed as an array of chromosomes,
each genetic operator along it´s
iterations/generations creates a new population.
There are special populations like the initial (P0) that
is created randomly, and the secondary population
(PS) used as an auxiliary place to save non-
dominated solutions (Piter - P.iteration and Pcand -
P.candidate).
Mutation - genetic operator, that depending on the
mutation probability changes a non-dominated
variable randomly. It is correlated to population
diversification but in high probability can decrease
convergence, [29].
Crossover is the combination between two fit
solutions, creating a descendant that saves partially
a portion of the genes of the two progenitors. The
genes distribution in the new progenitor solution can
be done according one-point, two-point splitting or
another pattern. Crossover type and probability
shape final population convergence performance,
[26], [29], [30].
Elitism - highest performance solutions are subject
to elitism, which prevent them from passing through
other genetic operators (cross-over, mutation,
selection) shielding them from possible degradation.
High elite array increases population stagnation and
can lead to local optimization solutions, [31].
Selection to select individuum’s to transit to the
next generation/iteration. The used methods of
selection can be: ranking, roulette wheel or
tournament. The AG that uses the tournament
selection, chooses randomly the best pair of
individuum’s to transit to the next generation, [29],
[30].
Tournament selection preserves population’s
diversification and is low computationally
demanding, [25], [32].
Robustness - practical implementation cannot be
done with ideal material or no tolerance on the
performance specification, also they are subject to
external variables non-accounted in the modulation.
A robust solution is defined as having a low
deterioration, when induced to disturbances. The
GA considers a solution with a high degree of
robustness when it is necessary in a distant radius of
simulated disturbance on input variables centered
from the considered solution, to decrease the
solution fitness in a determined radius from the
initial output fitness, [25], [32].
Sharing - it´s applied when NPS>NP, after solutions
with the best values in each objective function (Fn)
are inserted into the elite population then, a dynamic
niche is computed (ds=Maxdistance(F1, F2)/NPs)
and all the solutions at a distance greater then ds
from the ones already belonging to the elite are
inserted. If Ps remains unfilled, it will be
dynamically adjusted until the population has the
predefined size NPs, [25], [29].
A lot of AG variants are presented and
discussed in academic papers, in this paper we
focused on NSGA II (non-dominated sorting genetic
algorithm) as it grants fewer disadvantages than
other approaches, and also it seems to have a great
rated performance on testing MOP, [29]. NSGA II
application is expressed in Figure 5.
Fig. 5: Flowchart of the applied AG on multi-
objective problems, NSGA II, [25].
A dominates B and C
A is dominated by D
A is indifferent to E and F
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
220
Volume 18, 2023
5 Distribute ESS Problem
Formulation
This paper presents a problem of optimal placement
and sizing of ESS units on Cape Verde Islands EPS
where two objective functions are considered:
minimizing installation costs and minimizing
system losses. The used constraints are related with
service quality (bus voltage profile), networks
physical laws (obtained by power flow analysis) and
some technical restrictions (impossibility of
installation of certain ESS units at certain buses).
The result of the formulation expressed below,
represents a simplified notion of avoidable losses
that can be obtained by reducing power flow
between production and consumption buses. As
peak consumption increases DM usually increases
the network capacity or invests in distributed
generation to achieve loss reduction.
The major goal of this approach is finding, a
solution based on distributed storage, in order to
reduce transmission losses and at the same time
RES curtailment.
Thus, the implemented layout of the distribution
of ESS on the grid, should be formulated, regarding
to:
Minimize
[Cost installed storage; Power losses]
Subject to (
Power flow Equations
V, I Limits
PT power and space limitations
Installation costs are given by equation (1),
where, represent the binary decision
variables, that determines if a ESS can be installed
in a certain bus and is its acquisition cost, γ is its
storage capacity, α is the index related to a bus in a
secondary branch, β the branch identification and κ
the index of a bus number in the main branch.
The power losses minimization is given by equation
(2),
where, and are the corresponding active
and reactive power flow between the buses caused
by the resistivity of the power cable.
Power flow (active/reactive) between buses in a
secondary branch is given by equation (3) while
equation (4) refers to power flow on the main
branch, both depend on power generated
locally in the bus.
Equation (5) defines how voltage can be determined
for a given bus, while constrains (6) ensure that
energy quality in EPS is between acceptable
intervals defined by legislation.
In addition to the constraints of physical nature
related to the load flow equations, another
considered constraint (7) is the limitation imposed
that at most one ESS unit can be placed in each bus.
Based in historical electricity data, for this case
study, the peak consumption is assumed as
10,2MW, this value is taken from the most statically
representative month (July) sampled from 2018.
Sal Islands EPS distribution MV grid simplified
diagram is presented in Figure 6, as can be seen
demand peak loads are dispersed over buses as its
corresponding transformer capacity in each
community location, resident population and
touristic places.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
221
Volume 18, 2023
Fig. 6: Sal Island simplified MV network, taking
load distribution formulation using transformer post
capacity and a statistic consumer assumption.
The MV, 20kV, distribution grid is installed
underground in a star/radial topology. The main
branches have their starting point at the Diesel
Power Plant and ends on the RES generation buses.
Mainly, used cables are identified by LXHIOAV
with 120-240-500mm2 depending on the distance
and load. Two parallel cables go to bus 4 (Santa
Maria) which is divide in two but explored as an
open ring topology. All derived buses on the way
have a sectioning station connecting both cables,
guaranteeing the insolating of faults and power flow
transfer to the outer cable, improving reliability.
Being an underground grid, it creates a capacitive
effect (Ferranti effect) so reactive won´t be
accounted, [33].
Peak-hour transmission losses represent about
6-7% of annual losses. The Sal Island EPS annual
power losses are responsible for technical and
commercial losses of about 280.000€ every year;
losses costs are paid by the consumer through a
tariff compensation parcel. Electra undertook yearly
submission of a Loss Reduction Plan to ERA, thus
ESS can be used as well for RES integration.
6 Case Study
Wind energy curtailment is a long-standing issue on
Sal´s Island EPS, yearly it represents an average of
40% of the energy generated in the Wind Power
Plant as shown in Table 1. The curtailment causes
can be summarized by the oversized Wind Power
Plant installed capacity, made to anticipate an
energy consumption growth that didn’t occur;
possibly due to implementation logistics, to dilute
fixed engineering cost and project scale price
influence was greater than the oversizing cost.
Table 1. Wind energy curtailed vs. Wind farm
availability and used energy wind energy, between
2013 -2018 on the Sal Island network.
Also spinning reserve is not sufficient to
integrate all the wind energy available and it isn’t
economically viable for the EPS concessionary to
buy energy from Cabelólica´s high values
contractually defined. Electra tend to minimize
wind energy purchases, exploit low fuel market
prices and maximize its thermal capacity use to
repay its investment.
Regarding the power transmission losses, the
Island´s grid peak hour (19-20h) losses including
only MV cable represent 6-7% (~16k€) of the global
energy losses (~240k€/ 2% of produced energy),
which are accounted to the energy selling price.
Every five years, regulation obligates the
concessionary to reinvest a share of its profit, in an
energy losses mitigation plan which can create a
synergy between losses reduction and wind energy
integration, using an optimal ESS distribution on the
Island, [34].
The GA configuration
The GA methodology, described in section 4,
should receive input from a “.txt” file that describes
the EPS configuration and the available market
solution, so the algorithm can be able to
interactively generate (ESS allocation) and evaluate
(avoided losses/cost) a solution/individuum.
Electric data is stored in a matrix form, in which
columns divide them by types (resistance, start bus,
end bus, number of derivations, loads, generation)
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
222
Volume 18, 2023
and lines by a branch or bus index/code. Table 2
exemplifies some ESS solution codes and
characteristics inserted in the GA.
Table 2. Solution ESS power and its acquisition cost
codification used by the GA, arranged in 20kW step
corresponding to 17,7K€ steps.
ESS installation and operation best practice
Regarding the Diesel Power Plant management, it is
relevant that it limits ESS on Sal Island life cycle
between 30-50%, [35], so some suggestions to
overcome this, are:
inverters need a configuration to avoid batteries
from overheating (eg: outdoor installation);
use a PID (proportional, Integrative, derivative)
analyzed ratio of stored/colling energy when
curtailed wind energy is greater than storage
capacity;
use a predictive curtailment forecast
management to avoid charging on nominal
installed power.
To optimal enclosure of ESS in the grid, we
need to take into consideration the best place to
install it, so when feasible, the ESS should be
installed inside a concrete transformer substation
empty space or as close as possible to the substation
LV bus container or concrete building. The LV
integration of the ESS must be supported by a
technical study, which considers, the LV
substation´s empty space, load diagram, and
ventilation upgrade, in order to avoid overload when
the ESS is charging, personal risk, and cost
reduction. ESS allocation on the LV grid can use the
same allocation method as in the MV, not intended
in this paper.
The GA operator parametrization analysis
As a non-deterministic method used in this case
study GA operators are adjusted experimentally.
Being a small multi-objective problem, the
computational power processing required is low
about (15 minutes/100.000 generations). The best
parametrization is shown in Table 3.
Table 3. AG genetic operator, populations, and
iterations, best suited to find optimized ESS
allocation.
Operator adjustment guidelines were based on
papers, which state, [29], [32]:
Exclude domination and non-feasible
individuum on the initial population;
Crossover as the main operator since it is less
stochastic;
Mutation probability in an interval that
avoid random search or population stagnation;
Elite population enough to protect good
solution degradation.
Crossover method analysis
As mentioned before crossover is the main operator
used by the GA for the optimum solution
convergence. Thus it´s important to analyze the
crossover method’s influence on the optimum
solution convergence.
From Figure 7, we can conclude that Pareto
convergence is influenced by the crossover method.
Meanwhile, uniform cut and 2 cut-off methods
are more likely to distribute genes between the two
halves of the chromosome in the copy of the genes
to the descendant. The distributed copy of the genes
along the chromosome of the descendant, or damage
good solutions or improve the worst solutions, this
means that it increases intermediate solutions.
The possible explanation for the best
convergence of the one point cut-off crossover
method may be that, when copying the chromosome
of the parents from two halves, it guarantees a
greater probability for the descendant to conserve
the genes related to the installation of the ESS
concentrated in the first half of the grid buses [bus
1 to bus 8] in which these buses represent the
majority of the losses of the ESS (80%) and in the
second half buses [bus 9 to bus 15] receiving little
or no ESS installation, which allows a reasonable
performance to the descendant.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
223
Volume 18, 2023
Fig. 7: Crossover method influence analysis over
optimization gains.
RES variability compensation
Since the load distribution across the MV network
was assumed as fixed for modeling purpose based
on a statistic approach, to reflect the variability of
the Wind Power Plant, an energy injection scenario
method in (bus 5) is best suitable, overall it allows
to simplify the ESS gains effect.
Fig. 8: Wind Power Plant production effect on total
MV losses and observed Wind Power Plant hours of
defined production power, in 300kW intervals.
Figure 8 shows the Wind Power Plant’s
influence on power transmission losses. To
summarize all observed Wind Power Plant
production conditions, quartiles are used as
estimators to represent all sampled data, thus they
sum the sampled values in three scenarios with
statistical significance, as shown in Figure 9.
Fig. 9: Observed Wind Power Plant production
quartiles, set on a whisker plot.
Scenario Q1 1500kW RES, analysis
As defined, scenario Q1 represents the first quartile
of the sampled Wind Power Plant production
(1500kW), which leads a 28% (37,1kW) losses
reduction. Most of the losses, and decreases occurs
between bus 1-[...]-4 due to the bidirectional feeding
of bus 4 which represents 50,4% of the grid
consumption.
Other branches aren´t affected by RES
distributed production.
As a result, the last population found by the GA
is a Pareto curve formed by a solution with big loss
reduction/ investment cost ratio optimization.
Figure 10 shows the PF solutions obtained in
scenario Q1 and its linear correlation coefficient as
an optimization concavity/convergence optimization
capability index.
Fig. 10: Secondary population PF, computed by
NSGAII for scenario Q1 -1500kW RES, along
linear regression, and correlation.
It is visible that a reverse correlation between
losses/investment costs, is expected in this kind of
multi-objective problem. To notice solution indexes
are rearranged in ascending order, to simplify
analysis.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
224
Volume 18, 2023
Solution Q1-N1 minimizes cost, where losses
are reduced by 3% (2,9kW), corresponding to the
installation of a 100kW ESS and 89.000€
investment.
In comparation solution Q1-N31 minimizes
losses in 72%, which corresponds to the installation
of a 6,8MW ESS involving 6.000k€.
Optimized individuals have host of the allocated
ESS, on bus 4 which is the most energy-demanding
and farthest from Diesel Power Plant.
Making a population chromosomic analysis
from Table 4, in solution Q1-N16, we can see that
bus 4 cannot alone guarantee both objective
minimizations, so bus 8 turns out to be necessary.
Bus 8 is a large consumption bus connected by a
120mm2 cable, so is intelligible the appearance of
this gene/ESS. The solution Q1-N17 appearance,
may be explained by a similar minimization
performance and/or due to genetic operator effort to
maintain diversity.
Table 4. AG computed PF population chromosome
matrix and performance for scenario Q1- 1500kW
(1-losses kW; 2-cost k€).
Bus
1-3
4
5-7
8
9-10
11
12-15
L1
C2
Solution Index
0
0
0
0
0
0
0
0
96,9
0
1
0
5
0
0
0
0
0
94,0
89
2
0
10
0
0
0
0
0
91,2
178
3
0
19
0
0
0
0
0
86,3
338
4
0
28
0
0
0
0
0
81,6
498
5
0
34
0
0
0
0
0
78,7
605
6
0
39
0
0
0
0
0
76,3
693
7
0
45
0
0
0
0
0
73,6
800
8
0
53
0
0
0
0
0
70,1
942
9
0
60
0
0
0
0
0
67,2
1067
10
0
67
0
0
0
0
0
64,4
1191
11
0
77
0
0
0
0
0
60,8
1369
12
0
89
0
0
0
0
0
56,8
1582
13
0
101
0
0
0
0
0
53,2
1796
14
0
113
0
0
0
0
0
50,1
2009
15
0
122
0
0
0
0
0
48,1
2169
16
0
130
0
0
0
0
0
46,4
2311
17
0
131
0
0
0
14
0
43,4
2578
18
0
131
0
28
0
0
0
40,9
2827
19
0
130
0
41
0
0
0
39,0
3040
20
0
147
0
41
0
0
0
36,2
3343
21
0
158
0
41
0
0
0
34,8
3538
22
0
171
0
41
0
0
0
33,7
3769
23
0
144
0
81
0
0
0
31,6
4001
24
0
158
0
81
0
0
0
29,8
4250
25
0
173
0
81
0
0
0
28,6
4516
26
0
188
0
81
0
0
0
28,0
4783
27
0
147
0
135
0
0
0
27,8
5014
28
0
158
0
135
0
0
0
26,5
5210
29
0
173
0
135
0
0
0
25,2
5476
30
0
188
0
135
0
0
0
24,7
5743
31
0
194
0
145
0
0
0
24,4
6028
Now analyzing the PF solutions economic
performance, they correspond to a reduced watt loss
per thousand (W/k€) interval, between Q1-N1
32,8 W/k€ and Q1-N31, 12,3 W/k€. The middle
solution or nearest to the interval average is solution
Q1-N16, which makes it of course, the best trade-off
on both objectives.
Scenario Q2 3000kW RES, analysis
Secondly, scenario Q2 shows an intermediate RES
use situation (3MW), associated with the average of
the sample.
As a result, losses are reduced by 16%, lower
than in the Q1 scenario. Between buses 1-[...]-4
branches losses are lower, while losses between the
Wind Power Plant (bus 5) and bus 4 increases by
60%.
Figure 11, shows the Q2 solutions present at the
PF. After comparing Q1 and Q2, a linear regression
slope coefficient (Q1.m= -76/Q2.m= -118), shows
that the Q2 Pareto curve slope clearly reflects a
lower avoided losses/investment cost ratio in
comparison to scenario Q1. This happens because
most of the losses between buses 4-5 cannot be
reduced, by a distributed peak shaving ESS
dispatch, but through a production leveling
approach.
Fig. 11: Secondary population PF, computed by
NSGAII for scenario Q2 - 3000kW RES, along with
linear regression and correlation.
Incapability to reduce losses by allocating ESS
along the branch 4-5, as shown in Table 5 creates a
tendency to:
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
225
Volume 18, 2023
Q2 PF starts early to host ESS in a dispersed
approach (Between Q2-10 and Q2-15) on bus
11, also 3rd more responsible in power losses;
after the Q2-N16 individuum, ESS solutions
are more disperse and larger on bus 8, in
comparison to the same interval from Q1 PF.
Besides technical analysis is important for the
DM, an economic analysis, in this case, has fewer
optimization gains as stated before. The scenario Q2
population have a ratio of W/k€, between 7,84 and
20,7. It is important to note that the reduction of
RES is possible through the installation of larger
ESS’s, not accounted for in this analysis, but it has a
great and positive influence on economic
evaluation. Applying the same methodology to
define the best solution used before, solution Q2-
N14 evidently manages to have similar gains on
both goals, as having a W/k€ nearest from the Q2
last computed population average (13,62W/k€).
Table 5. AG computed PF population chromosome
matrix, Q2-3000kW (1-losses kW; 2-cost k€).
Scenario Q 3 3900kW RES, analysis
The last scenario is Q3, which refers to the
upper/third quartile (3,9MW) of the observed wind
energy injection, on bus 5.
In this scenario, losses increase by 7% when
related to wind absence, in contrast to a higher RES
power injection, from the Wind Power Plant,
reducing fossil fuel consumption, reducing
dependence and shortening distance to carbon
neutrality.
Energy transmission losses are lowered,
between bus 1-[...]-4 which before were 55,5% of
total losses now are 5,7%. However, this gain, is
surpassed by the loss increase between the Wind
Power Plant bus 5 and bus 4, now responsible for
76,3% of the grid technical losses.
Fig. 12: Secondary population PF, computed by
NSGAII for scenario Q3 - 3900kW RES, along with
linear regression and correlation.
From Figure 12, we can conclude that the
tendency of avoided losses/investment cost ratio
continues to decrease. Now the linear regression
slope is -137 (Q2.m-118, Q1.m -76,47).
Linear correlation is also an optimization gain
indicator, increases in this scenario Q3.r2 0,957
(Q2.r2 0,926; Q1.r2 0,899) which are responsible
for lower objectives minimizations, because it
reflects a PF with a lower concavity.
For this scenario, it is possible to see in Table 6
that solutions are earlier divided and less centralized
on bus 4. Now bus 8 is the third bus with more
consumption on the EPS receiving more allocation
of ESS, because most of the losses of the branches
Bus
1-3
4
5-7
8
9-10
11-15
L1
C2
Solution Index
0
0
0
0
0
0
0
112,5
0
1
0
6
0
0
0
0
110,3
107
2
0
13
0
0
0
0
107,9
231
3
0
20
0
0
0
0
105,7
356
4
0
24
0
0
0
0
104,4
427
5
0
28
0
0
0
0
103,3
498
6
0
33
0
0
0
0
101,9
587
7
0
39
0
0
0
0
100,3
693
8
0
46
0
0
0
0
98,6
818
9
0
53
0
0
0
0
97,1
942
10
0
53
0
0
0
6
95,8
1049
11
0
59
0
0
0
6
94,6
1156
12
0
69
0
0
0
6
92,8
1334
13
0
59
0
0
0
24
91,3
1476
14
0
66
0
0
0
24
90,1
1600
15
0
75
0
0
0
24
88,7
1760
16
0
64
0
43
0
0
87,3
1903
17
0
76
0
43
0
0
85,4
2116
18
0
75
0
54
0
0
84,0
2294
19
0
84
0
54
0
0
82,8
2454
20
0
95
0
54
0
0
81,7
2649
21
0
79
0
77
0
0
80,8
2774
22
0
87
0
77
0
0
79,8
2916
23
0
96
0
79
0
0
78,8
3112
24
0
95
0
91
0
0
77,8
3307
25
0
92
0
110
0
0
76,7
3592
26
0
105
0
110
0
0
75,7
3823
27
0
103
0
121
0
0
75,3
3983
28
0
108
0
126
0
0
74,9
4161
29
0
122
0
126
0
0
74,5
4410
30
0
109
0
154
0
0
74,3
4676
31
0
122
0
154
0
0
74,0
4907
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
226
Volume 18, 2023
between buses 4-5 cannot be avoided by a peak
shaving dispatch.
In addition, in this scenario using the same
method of economic analysis, we can see that the
population ratio represents a lower gain for the EPS
and a greater demand in investment for the DM. The
scenario Q3 population, avoided losses/investment
cost is between Q3-N31 6,35W/k€ and Q3-N1
13,43W/k€, being solution Q3-N15 the one with the
better balance in both goals (with results in W/k€
near to the Q3 population average).
Table 6. AG computed PF population chromosome
matrix and performance for scenario Q 3- 3900kW
(1-losses Kw; 2-cost k€).
Scenarios (Q1, Q2 and Q3), sensibility analysis
To apply the best solution, the DM should take into
account the following: the EPS dispatch protocols,
funds available for investment, technological
advancement and other aspects.
Making a fast analysis related to the technical-
economic goals, based on data used in this paper
and considering the DM role, can be assumed that:
Low power ESS, should be avoided, because
they reduce fixed costs compensation
(engineering, construction and logistics) and
negotiating power;
ESS solutions with installed power between
1MW to 4MW offer an excellent EPS loss
minimization gain, they have a reduced wind
energy curtailment avoidance;
Above 4MW ESS, solutions have a reduced
effect on EPS losses mitigation, so they must
be excluded.
The analysis should be located between, 1 and
4MW intervals where are the intermediate solutions
Q1-N16, Q2-N14 and Q3-N15.
Typical scenarios were developed by quartile
and interquartile which divides observed wind space
in four. The space above and under the first and
third quartile (25%) is overlapped by the space of
the third or mean quartile, to compensate that Table
6, shows the “weight” used as a coefficient in the
sum of each plot.
Table 6. Coefficient use in Weight Sum, for avoided
losses analysis.
The solution with the best sensibility gain is
solution Q1-N16, as shown in Table 7, using Table
6 coefficient to sum its performance on the
complementary scenarios and its main scenario, it´s
possible to obtain 28kW, or 23% taking into account
the weight sum losses in RES absence that is
119kW.
Table 7. Weight sum and avoided losses sensibility,
for intermediate solutions on original and
complementary scenarios.
7 Economic Internalities
The Identification of all the variables that may affect
the final result is difficult, but it is an aspect that the
DM must have in mind.
Having a projected actualization rate of 3,5%
(obtained by summing the Cape Verdean low-risk
investment interest and inflation) and a 15-year first
phase project lifetime, the expected expenses are:
- ESS acquisition, which includes engineering,
installation and commissioning, with a cost of
450k€ per MW, [36], [37];
Bus
1-3
4
5-7
8
9
10-15
P1
C2
Solution index
0
0
0
0
0
0
0
144,9
0
1
0
6
0
0
0
0
143,5
107
2
0
12
0
0
0
0
142,1
213
3
0
17
0
0
0
0
141,1
302
4
0
23
0
0
0
0
140,0
409
5
0
29
0
0
0
0
139,0
516
6
0
10
0
25
0
0
137,9
622
7
0
15
0
25
0
0
136,8
711
8
0
23
0
25
0
0
135,3
853
9
0
29
0
25
0
0
134,3
960
10
0
28
0
31
0
0
133,5
1049
11
0
33
0
31
0
0
132,7
1138
12
0
34
0
39
0
0
131,3
1298
13
0
42
0
39
0
0
130,2
1440
14
0
34
0
54
0
0
129,2
1565
15
0
38
0
58
0
0
128,1
1707
16
0
46
0
58
0
0
127,1
1849
17
0
46
0
65
0
0
126,3
1974
18
0
41
0
77
0
0
125,6
2098
19
0
47
0
77
0
0
124,9
2205
20
0
53
0
77
0
0
124,3
2311
21
0
46
0
90
0
0
123,8
2418
22
0
53
0
90
0
0
123,1
2543
23
0
61
0
90
0
0
122,5
2685
24
0
62
0
101
0
0
121,6
2898
25
0
61
0
110
0
0
121,1
3040
26
0
67
0
112
0
0
120,7
3183
27
0
77
0
112
0
0
120,4
3360
28
0
69
0
130
0
0
119,8
3538
29
0
79
0
130
0
0
119,6
3716
30
0
74
0
144
0
0
119,4
3876
31
0
83
0
144
0
0
119,3
4036
Scenario
Q1
Q2
Q3
Coefficient
0,4
0,2
0,4
Avoided
losses
(kW)
Scenario
Q1
Q2
Q3
Weight Sum
Q1-N16
-50
-22,8
-7,2
28
Q2-N14
-35,5
-23,3
-14,6
25
Q3-N15
-30,2
-21,6
-11,7
21
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
227
Volume 18, 2023
- Maintenance, to achieve the expected lifetime
of the ESS, these should be subject to a maintenance
plane. The maintenance plan is divided into fixed
maintenance costs and variable maintenance costs.
The typical costs are 8,6€/kW and 2,6€/kWh
respectively, [36].
The positive cash-flow of the project is given by
the following subjects:
- Carbon credit, a mechanism that financially
supports sustainable development. Avoided
CO2(Ton/MW), an index which is sold by
Caboéolica for 0,5€/MWh;
- Energy sold, stored energy sold price is the
same used by Caboéolica RES price of 0,15€/kWh.
Yearly it´s expected the usage of 92% of the
storage capacity, based on 2018 wind injection in
the grid, with a total ESS efficiency of 92% in a
complete charge/discharge battery cycle.
In this analysis the DM is Caboeólica, with the
avoided losses of EPS being a counterpart for
Electra to receive stored RES that otherwise would
be curtailed.
The Profitability study, of both phases results is
given in Table 8, using as indicators pay-back time,
internal return rate (IRR) and net present value
(NPV), [38]; which have low expression a the first
investment phase. But in a second phase that relies
only on the battery exchange it has a great gain for
the DM with an investment value of (135,1k€/MW).
Table 8. Economic indicators result, for ESS
investment.
This case study shows how energy tariffs can be
reduced, because the RE yearly tariff actualization
formula, has a reduction effect based on total RES
integration in the archipelago. The ESS based on
RES curtailed energy will decrease by 1,74% fossil
fuel contribution on the energy tariff.
8 Conclusion
The methodology used in this paper, to model RES
curtailment integration, having in mind the
economic and technical limitation, can be used as a
framework for similar EPS. The initial problem of
allocation and sizing ESS on the EPS aims to:
minimize of total power losses and minimize of ESS
costs.
To solve this multi-objective problem, a GA
was applied, whose PF presents a set of distributed
solutions that can be used by the DM for practical
implementation.
Intuitively, it´s possible to say that the highest
consumption buses are the best candidates to
allocate ESS, the GA excludes the existence of a
small dispersion that may have outweighed this
deduction.
Also, the environmental and economic aspect
heavily contributes to all interested players in the
EPS (Electra, Cabolica and consumers).
Another crucial observation that can be taken
from this paper and case study is the importance of
integrating more RES combined with ESS on the
power grid and its direct relation with its strong
contribution to global "carbon neutrality" and
energy efficiency. These two technologies should be
intrinsically linked because RES are characterized
as being intermittent and not dispatchable. The
symbiosis between RES and ESS allows RES to be
used with better performance, making better use of
the energy generated by them, avoiding wasted
energy, when these technologies are operating in
over power production (excess of production faced
with low load demand). This way it´s possible to
allocate renewable energy production stored in ESS
to be used in periods of greater consumption or
absence of renewable production avoiding the
operation of fossil fuel technologies and all their
economic and Environmental externalities.
This methodology and its implementation in a
real case study, shows how the use of a
mathematical tool can be useful as a decision
support for EPS DM’s. In future this decision
support system may be integrated in in a non-radial
Islands Power Grid or in a wider Grid of a
continental country divided in Virtual Power Plant´s
Active Power Grids.
References:
[1] Gesto Energia SA, Cape Verde Energy Plan
(Plano Energético Cabo Verde), Gesto Energy
Solutions, Algés, 2011, [Online],
http://www.ecowrex.org/system/files/docume
nts/2011_plano-energetico-renovavel-cabo-
verde_gesto-energia.pdf (Accessed Date:
April 5, 2022).
[2] B. Ahmadi, O. Ceylan, A. Ozdemir, "A multi-
objective optimization evaluation framework
for integration of distributed energy
resources", Elsevier, Journal of Energy
Storage, Vol. 41, September 2021, 103005
[3] B. N. Alajmi, M. F. AlHajri, N. A. Ahmed, I.
Abdelsalam, M. I. Marei, "Multi-objective
Optimization of Optimal Placement and
Phase 1
Phase 2
Pay-back
12
1
IRR
282 k€
2.209k€
NPV
5,3%
31,45%
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
228
Volume 18, 2023
Sizing of Distributed Generators in
Distribution Networks", Transaction on
Electrical and Electronic Engineering, Wiley,
2023, https://doi.org/10.1002/tee.23784.
[4] Martins, A. G., Antunes, A. H., Santos, V. E.,
“A Multi-objective Decision Support
Framework for Distributed Generation
Planning”, AIESP Conference Madeira
Island, Feb. 2006.
[5] Deb K., “Multi-Objective Optimization using
Evolutionary Algorithms”, Wiley, 2001,
ISBN: 978-0-471-87339-6.
[6] Salt Island (Ilha do Sal), Wikipedia, 2022,
[Online],
https://pt.wikipedia.org/wiki/Ilha_do_Sal
(Accessed Date: April 19, 2022).
[7] ECREEE Secretariat, "Summary of Cape
Verde Renewable Energy Plan", ECREEE,
2011, [Online],
http://www.ecowrex.org/system/files/docume
nts/2011_summary-of-cape-verde-renewable-
energy-plan_ecreee.pdf (Accessed Date: April
20, 2022).
[8] A. S. Muñoz, M. Gerlich, and M. Garcia,
"Overview of storage technologies", Sensible,
Jan.2016, [Online],
https://www.projectsensible.eu/documents/ov
erview-of-storage-technologies.pdf (Accessed
Date: April 20, 2022).
[9] "Electric Energy Storage Technology
Options: A White Paper Primer on
Applications, Costs, and Benefits", p.170.
EPRI, Palo Alto, CA, 2010. 020676.
[10] Report and Accounts-Caboéolica 2013-2018,
Cape Verde (Relatório e Contas-Caboéolica
2013-2018, Cabo Verde), [Online],
https://www.cabeolica.com/site1/site1/sobre-
nos/relatorio-e-contas/ (Accessed Date: April
21, 2022).
[11] Cape Verde Wind Project Case Study (Estudo
de Caso Projeto Eólico da Caboeólica Cabo
Verde Caboeólica), CEDEAO, Nov. 2017,
[Online],
http://www.ecreee.org/sites/default/files/ecree
e_estudo_de_caso_projeto_eolico_da_cabeoli
ca_cabo_verde.pdf (Accessed Date: April 21,
2022).
[12] S. G. Abelho, Electrical energy storage:
scenarios for the Portuguese electrical system
(Armazenamento de energia eléctrica:
cenários para o sistema eléctrico Português),
FCT-DCEA, 2011, [Online],
https://run.unl.pt/handle/10362/7778
(Accessed Date: April 21, 2022).
[13] F. Nadeem, S. Hussain, P. Tiwari, A.
Goswami, and T. S. Ustun, "Comparative
Review of Energy Storage Systems, Their
Roles and Impacts on Future Power Systems",
IEEE Access, vol. 7, pp. 4555–4585, Jan.
2019, doi: 1.1109/ACCESS.2018.2888497.
[14] T. M. Letcher, "Storing Energy: with Special
Reference to Renewable Energy Sources",
Elsevier, 2016,
https://doi.org/10.1016/C2020-0-00604-3.
[15] X. Luo, J. Wang, M. Dooner, and J. Clarke,
"Overview of current development in
electrical energy storage technologies and the
application potential in power system
operation, Applied Energy", vol. 137, pp.
511–536, Jan. 2015,
https://doi.org/10.1016/j.apenergy.2014.09.08
1.
[16] High view Power, Liquid air energy storage
Plants, [Online],
https://www.highviewpower.com/plants/
(Accessed Date: May 20, 2022).
[17] Thermal Energy Storage - Newsol
(Armazenamento de Energia Térmica),
[Online], http://www.newsol.uevora.pt/pt-
pt/tecnologia-tes/ (Accessed Date: June 4,
2022).
[18] M. J. Baumann, "Battery storage systems as
balancing option in intermittent renewable
energy systems - A transdisciplinary approach
under the frame of Constructive Technology
Assessment", FCT-DCSA, 2017, [Online],
https://run.unl.pt/handle/10362/31566
(Accessed Date: June 4, 2022).
[19] J. G. Kim, B. Son, S. Mukherjee, N.
Schuppert, A. Bates, O. Kwon, M. Choi, H.
Chung, S. Park, "A review of lithium and non-
lithium based solid state batteries", Journal of
Power Sources, no. 282 (2015), pp. 299–322,
https://doi.org/10.1016/j.jpowsour.2015.02.05
4.
[20] S. K. Suraparaju, S. Natarajan, and P.
Karthikeyan, "A succinct review on fuel
cells", IOP Conference Series: Earth and
Environmental Science, vol. 312, p. 012012,
Oct. 2019, doi: 10.1088/1755-
1315/312/1/012012.
[21] "Hydrogen" fuel (Combustível "hidrogénio")
Millenium - Journal of Education,
Technologies, and Health, 2019, [Online],
https://revistas.rcaap.pt/millenium/article/view
/8428 (Accessed Date: August 22, 2022).
[22] E. García and I. Leilani, "Fundamental and
Flow Battery Studies for Non-Aqueous Redox
Systems", Case Western Reserve University,
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
229
Volume 18, 2023
2015, [Online],
https://etd.ohiolink.edu/pg_10?::NO:10:P10_
ETD_SUBID:101393 (Accessed Date: July 2,
2022).
[23] Irene Fastelli, "Energy Storage On Islands: A
sustainable energy future for islands",
EURELECTRIC Brussels, Mar. 10, 2012,
[Online],
https://www3.eurelectric.org/media/64743/Fas
telli.pdf (Accessed Date: September 2, 2022).
[24] Energy Storage Solutions, "Hybrid Wind,
Solar & Energy Storage Power Plant Graciosa
Island", Leclanché, 2019, [Online],
https://www.leclanche.com/wp-
content/uploads/2019/04/LECLANCHE-
GRACIOSAWEB.pdf (Accessed Date:
January 9, 2023).
[25] V.Santos, A Multi-Objective Approach to
Including Dispersed Generation in Electricity
Production Expansion Planning ("Uma
Abordagem Multi-Objectivo para a Inclusão
da Geração Dispersa no Planeamento da
Expansão da Produção de Energia Eléctrica"),
PhD Thesis, FCTUC, Coimbra, 2011.
[26] C. A. Coello and G. B. Lamont, "Evolutionary
Algorithms for Solving Multi-Objective
Problems", Second Edition, Springer US,
2001, [Online],
https://link.springer.com/book/10.1007/978-0-
387-36797-2 (Accessed Date: November 2,
2023).
[27] C. M. Fonseca and P. J. Fleming, "Genetic
Algorithms for Multiobjective Optimization:
Formulation, Discussion and Generalization".
Proceedings of the ICGA-93: Fifth
International Conference on Genetic
Algorithms, 17-22 July 1993, San Mateo, 416-
423.
[28] Kleber Hashimoto, Multi-objective
combinatorial optimization techniques applied
to estimate the electrical performance of
distribution networks ("Técnicas de
otimização combinatória multiobjetivo
aplicadas na estimação do desempenho
eléctrico de redes de distribuição"), EPUSP,
2004, https://doi.org/10.11606/T.3.2004.tde-
19112004-165342.
[29] L. Costa, Evolutionary algorithms in uni- and
multi-objective optimization ("Algoritmos
evolucionários em optimização uni e multi-
objectivo"), PhD Thesis, UM 2003.
[30] I. L. de S. Russo, Multi-objective optimization
and genetic programming for engineering
knowledge discovery ("Otimização
multiobjetivo e programação genética para
descoberta de conhecimento em engenharia"),
UFJF, 2017, [Online],
https://repositorio.ufjf.br/jspui/handle/ufjf/409
7 (Accessed Date: November 2, 2023).
[31] S. B. Fonseca, Optimal allocation of wind
farms in distribution systems considering
wind and load uncertainties using genetic
algorithm ("Alocação ótima de parques
eólicos em sistemas de distribuição
considerando incertezas de vento e carga
utilizando algorítmo genético"), RIUFPA,
2016, [Online],
https://repositorio.ufpa.br/jspui/handle/2011/8
305 (Accessed Date: November 2, 2023).
[32] C. M. C. S. Barrico, Multi-objective
evolutionary optimization in uncertain
environments: search for robust solutions
("Optimização evolucionária multi-objectivo
em ambientes incertos : pesquisa de soluções
robustas"), UBI, 2007, [Online],
https://www.di.ubi.pt/~cbarrico/Doutorament
o/Download/TeseDoutoramento.pdf
(Accessed Date: November 2, 2023).
[33] J. P. S. Paiva, Electricity Networks. A
Systemic Analysis ("Redes de Energia
Elétrica. Uma Análise Sistêmica"), 3rd
Edition, IST Press, 2007.
[34] ARME, Order 14/2011, Tariff Regulation for
the Electricity Sector ("Despacho 14/2011,
Regulamento Tarifário do Sector Eléctrico"),
[Online],
https://www.arme.cv/index.php/arme/docume
ntacao/download/332-despacho-n-14-2011-
regulamento-tarifario-do-sector-electrico,
(Accessed Date: January 9, 2023).
[35] E. Lockhart, X. Li, S. Booth, J. Salasovich, D.
Olis, J. Elsworth, L. Lisell, "Comparative
Study of Techno-Economics of Lithium-Ion
and Lead-Acid Batteries in Micro-Grids in
Sub-Sahrian Africa". National Renewable
Energy Laboratory, Technical Report
NREL/TP-7A40-73238, June 2019.
[36] W. Cole, C. Marcy, V. Krishnan, and R.
Margolis, "Utility-scale lithium-ion storage
cost projections for use in capacity expansion
models", Sep. 2016, pp. 1–6.
doi: 10.1109/NAPS.2016.7747866.
[37] "Handbook on battery energy storage system",
Asian Development Bank, Dec. 2018,
[Online],
https://www.adb.org/publications/battery-
energy-storage-system-handbook (Accessed
Date: November 2, 2023).
[38] F. J. Candian, Expansion planning of
electrical distribution systems considering risk
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
230
Volume 18, 2023
factors in economic analysis ("Planejamento
da expansão de sistemas elétricos de
distribuição considerando fatores de riscos em
análise econômica"), UNESP, 2008, [Online],
https://www.cgti.org.br/publicacoes/wp-
content/uploads/2016/01/Planejamento-da-
Expansa%CC%83o-de-Sistemas-de-
Distribuic%CC%A7a%CC%83o-
Considerando-Fatores-de-Riscos-em-
Ana%CC%81lise-Econo%CC%82mica.pdf
(Accessed Date: November 2, 2023).
Contribution of Individual Authors to the
Creation of a Scientific Article (Ghostwriting
Policy)
The authors equally contributed in the present
research, at all stages from the formulation of the
problem to the final findings and solution.
Sources of Funding for Research Presented in a
Scientific Article or Scientific Article Itself
No funding was received for conducting this study.
Conflict of Interest
The authors have no conflicts of interest to declare.
Creative Commons Attribution License 4.0
(Attribution 4.0 International, CC BY 4.0)
This article is published under the terms of the
Creative Commons Attribution License 4.0
https://creativecommons.org/licenses/by/4.0/deed.en
_US
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.23
Denis Santos, Vasco Santos
E-ISSN: 2224-350X
231
Volume 18, 2023