Power System Control Centers and Their Role in the Restoration
Process after a Major Blackout
GEORGIOS FOTIS, CHRISTOS PAVLATOS, VASILIKI VITA
Department of Electrical and Electronics Engineering Educators, ASPETE,
School of Pedagogical and Technological Education of Athens,
N. Heraklion, 14121,
GREECE
Abstract: - Power control centers have evolved since their ground-breaking inception in the 1960s, and they
are extremely important for the operation of the power system, ensuring maximum reliability. There has been
much discussion about mandating reliability requirements, but for the most part, reliability standards are
already in place for electricity grid design and operation. Unfortunately, these standards do not examine in
detail monitoring and control, possibly due to the false belief that reliability primarily comes from redundancies
in transmission and generation. The grid can operate even more closely to its limits thanks to improved grid
control and monitoring, which also increase reliability. In this paper, the significant role of the power system
control centers in the event of a major blackout is discussed, proving their significance in the restoration
process.
Key-Words: - Blackout, Power Energy Control Centers, Transmission System Operators, Restoration plan,
Stability
Received: July 14, 2022. Revised: January 17, 2023. Accepted: February 22, 2023. Published: March 28, 2023.
1 Introduction
A practical dispatching automation system has been
steadily developed over the years and is crucial to
ensure the reliable operation of the power grid.
However, there is a significant disconnection
between the current standards and the ongoing
growth of the power system, particularly in the
following areas: (1) As the electricity grid's
operating characteristics become more complex, the
difficulty of security control follows as well; (2) in
an economic dispatch, the need of energy saving is
increasing; and (3) the optimization level of power
system operation needs improvement, [1], [2], [3].
Worldwide, blackouts occur regularly every day,
[4]. Most are brief and have minimal bearing on
consumers without access to power, [5]. However
large blackouts that had a big impact have happened
all around the world over the past 20 years, [6], [7].
In recent decades there is a turn in renewable energy
sources such as solar and wind energy to reduce the
CO2 emissions that affect the world’s climate, [8].
Recent research works have shown the necessity of
renewable energy sources in a power system for the
reduction of CO2 emissions, [9], [10]. Using other
energy sources different than fossil fuels may have
risks but their use is preferable in techno-economic
terms, [11]. The penetration of renewable energy
sources must follow certain rules ensuring
scalability and replicability, [12]. However,
Variable Renewable Energy Sources (VRES)
intrinsic variability decreases the power system’s
reliability, in severe weather conditions, [13]
proving the need for energy storage and flexibility
of the power system, [14]. From this fact is clear
that in a power system, a blackout risk is always
present with an unpredictable impact on the society
and the economy, [15], [16]. It must be mentioned
here that this high penetration of VRES also affects
the power quality of the grid as the voltage levels,
[17], [18], that may cause voltage collapse and a
possible blackout, [15].
There isn't a single solution to the question of
figuring out the ideal VRES penetration, [19], and
quantity of storage, [20], but various standards
might apply in each instance, [21]. Also, despite the
fact that almost every country in Europe has a
connected power system and that the European
Network of Transmission System Operators for
Electricity (ENTSO-E) has provided guidelines for
the European grid, [22], [23], [24], [25], [26], [27],
[28], [26], there is always a chance of a significant
disruption or, even worse, a complete blackout.
Reduction of losses and restoration time,
minimization of adverse social effects, and quick
and safe return of the power system to regular
operation are the goals of restoration. The
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
57
Volume 18, 2023
development of restoration methods has made
extensive use of non-structured approaches,
technologies, and object-oriented expert systems to
accomplish the goals, [30]. As computational
intelligence has advanced, some intuitive
algorithms, including genetic algorithms, [31],
artificial neural networks, [32], and fuzzy logic,
[33], are used to restore systems. Based on the
regional distribution features in space, multi-agent
technologies, [34], [35], [36], [37], have been
created with promise. Expert systems and heuristic
rules are effectively extended by decision support
systems, [38].
For the efficient use of a power system, the
loadability limits must be calculated online.
Maximum loadability limits were formerly
calculated in power system control centers using
time-consuming simulations and off-line studies,
which were particularly difficult to be done when
stability considerations were included. There are
now straightforward applications that can determine
very fast how unstable is a certain operating state.
The goal after a blackout is to restore the power
system. In this process, the power system control
centers (PSCC) have a significant role. In the
current work the main principles of the power grid’s
stability, the role of the PSCCs, and basic guidelines
after a blackout are presented. This paper also
emphasizes the dispatcher's significance in the event
of a major blackout. If a dispatcher is not competent
and well-trained, the restoration plan as it will be
described in section 6 will not be possible to be
carried out. This work also examines and shows that
a power system cannot be operated just by fast and
intelligent software tools, but it also heavily relies
on human skills and abilities. The restoration
requires dispatchers who can adapt it to the current
state of the transmission system.
The structure of this work is as follows. The
significance of the PSCC and its role in the
electricity system is discussed in section 2. The
dispatchers, who work in these centers, are familiar
with the monitoring importance and a thorough
examination of the hardware and software systems
that the PSCCs are based on, so they are prepared to
handle any issue that might arise in the transmission
system. Section 3 presents the evaluation of the
power system state, and Section 4 analyzes the
assessment of steady-state stability. The design of
the dynamic security evaluation in a PSCC is
provided in section 5, and the restoration plan and
the steps that must be taken after a significant
blackout are thoroughly examined in section 6. The
two final sections, 7 and 8, provide the concluding
notes.
2 Power System Control Centers
(PSCC)
2.1 The Main Scope of a PSCC
A fundamental design feature of PSCC is that it
increases system reliability and economic feasibility
by performing Energy Management (EM), [39],
[40], [41], [42]. The PSCC has existed for decades
as the interconnected system's central decision-
making body for electric transmission and
production has been extended as well. It performs
the tasks required for supervising and organizing the
electricity system's economic and physical
operations on a minute-by-minute basis. An
interconnected electricity system needs carefully
coordinated decision-making to maintain its
integrity and economy. As a result, one of the
PSCC's main responsibilities is to regulate and
monitor the physical functioning of the connected
grid. A high-level view of the PSCC is illustrated in
Figure 1, where we can identify the SCADA system
with the related telemetry and communications
equipment with all the elements of the power system
(circuit breakers, disconnectors, etc.) and how the
software applications of the Automatic Generation
Control (AGC) are implemented in it.
Figure 1 is a schematic diagram illustrating the
information flow between various computer-based
tasks to be carried out in a PSCC. Remote terminal
units (RTUs), which encode measuring transducer
outputs and opened/closed status information into
digital signals and transfer them to the operations
center across communication circuits, provide the
system with information on the power system. The
PSCC can communicate control data, such as set
points to raise or lower the speed of generators, and
commands to open or close circuit breakers (CBs).
Analog measurements and breaker/switch status
indications are also data entering the control center.
The Automatic Generation Control (AGC) program
must use the analog measurements of generator
outputs directly, but all other data must first go
through the state estimator before being used by the
other programs.
The control in PSCC consists of the three
following levels:
Level 1: Instantaneous control of the turbine
governor, which adjusts generation to balance
changing load.
Level 2: The ACG, also known as load
frequency control (LFC), repeats the process
every 2 to 6 seconds to keep frequency and net
power interchange.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
58
Volume 18, 2023
Level 3: Economic Dispatch divides the load
amongst the units such that the fuel cost is
minimized at intervals of 5 to 10 minutes.
The PSCCs are also in charge of the main
voltage control in the power system for:
The generator bus voltage, regulated by
excitation controls.
The Static VAR Controllers (SVC), shunt
capacitors, transformer taps, and other
transmission voltage control devices.
Fig. 1: Schematic diagram of the information flow between various computer-based tasks carried out in a
PSCC.
2.2 Automatic Generation Control (AGC)
To adjust the generation against the load at the
lowest possible cost, AGC consists of two main and
a number of minor functions that run in real-time
online. Load frequency control and economic
dispatch are the two main tasks, and each is
explained in detail below. Interchange scheduling,
which starts and finishes scheduled interchanges,
reserve monitoring, which ensures there is enough
reserve on the system, and other comparable
monitoring and recording operations are the minor
functions.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
59
Volume 18, 2023
2.3 Monitoring
An energy control center performs the task of
coordinating the system components' responses
during both routine operations and emergency
situations. In typical circumstances, the digital
computer is given the responsibility of repetitive
control, while human operators do selected
monitoring. The incoming stream of data is
processed by the digital computer to look for
anomalies, and the human operator is alerted by
lights, buzzers, and monitor presentations. Digital
computers frequently handle much lower-level or
less serious incidents of exceeding normal
boundaries. Normal control operations might be
suspended if the digital computer detects a more
serious problem. Many alerts may be found in
emergency situations, such as the failure of a
significant generator or excessive power demands
placed on tie lines by a nearby utility. In these
situations, the system may enter an emergency
status.
2.4 Data Acquisition and Control
Data acquisition supplies the status and
measurement data required to oversee the overall
operations of computer control systems. The
purpose of security control is to establish operating
conditions by analyzing the effects of errors
between the master station and remote terminal unit
(RTU) of a Supervisory Control and Data
Acquisition system (SCADA). To observe and
manage power plants, the master station sends data
to the RTU. At generating stations, transmission
substations, and distribution substations, RTUs are
placed. RTUs broadcast measurements and device
status to the master station, and they also receive
control instructions from the master station.
The steady-state reading can be simultaneously
gathered from numerous instrument sites and
preserved for later analysis using a computer-aided
data-collecting technique. Voltage or current
variations could be the outcome of the transient. It
can be challenging to pinpoint the transient's origin
in a real power system, where it may cause
component failure. The transients can be lowered
and analyzed using a data acquisition system.
2.5 Phasor Measurement Units (PMU) for
Power Systems
A PMU is a device that determines the phase angle
and magnitude of an electrical phasor quantity (such
as current or voltage) in the electrical grid using a
shared time source for synchronization. PMUs can
rapidly reconstruct the phasor quantity—which
consists of measurements of both an angle and a
magnitude—using samples from a waveform. These
time-synchronized data are essential because
frequency imbalances can strain the grid's supply
and demand, which could result in power outages.
PMUs can gauge the electrical frequency of the
power grid. A typical PMU may report
measurements up to 120 times per second with a
very high temporal resolution.
Unlike traditional SCADA measurements, which
generate a measurement every two to four seconds,
engineers can now analyze dynamic grid events. As
a result, PMUs give utilities improved monitoring
and control capabilities, making them one of the
most crucial measuring tools for the development of
power systems. A PMU can be a separate device, or
it can be integrated with another device, such as a
protective relay, to perform the PMU function.
EMS and SCADA are examples of existing
power grid technologies that can only provide a
steady state picture of the power system with a high
data flow delay. Due to technical issues
synchronizing measurements from various
locations, it is not possible to use SCADA to
measure the phase angles of bus voltages of the
power system network in real-time.
Measurements were made more slowly, and the
operator only received a limited amount of
information on the power system's dynamic
behavior. By synchronizing voltage and current
waveforms at separated places, PMUs helped to
solve this issue. PMU outperforms SCADA in terms
of performance, reliability, and speed.
A PMU is a device that uses voltage, current,
and/or time synchronizing signals to estimate
frequency, rate of change of frequency, and phasor.
PMUs use Global Positioning System (GPS) signals
to give real-time synchronized measurements in the
power system with better than 1 ms synchronization
precision. In power system substations, PMUs
measure the time-stamped positive sequence
voltages and currents of all the tracked buses and
feeders. A suitable location is chosen for the
collection of data from several substations, and a
coherent image of the state power system is
produced by lining up the time stamps of
measurements.
The major applications of the PMUs are:
Monitoring thermal overloads
Analysis of disturbances
Stability monitoring
Restoration of the power system after a
blackout
State estimation
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
60
Volume 18, 2023
Control in real time
Adaptive protection
2.6 System Hardware Configuration
A small number of operators can keep an eye on the
generating and high voltage transmission system
thanks to the supervisory control and data
acquisition systems. Electric utilities almost always
use a redundant set of dual digital computers for the
purposes of remote data acquisition control, energy
management, and system security in accordance
with the concepts of high reliability and fail-safe
failures.
The online units, which are typically one
computer, monitor and manage the power system.
Off-line batch applications like load forecasting or
hydro-thermal allocation might be running on the
backup computer. A shared disk memory between
the two computers is frequently updated by the
online computer. The common disk's stored data is
loaded into the online computer's memory in
response to a failure over or switch-in status
instruction.
The online computer's information has a
maximum age of updating cycle. Using input-output
microprocessors that have been configured to
interact, as well as pre-process the analog
information, check for limits, convert to another
system of units, and other tasks, all peripheral
equipment is connected to the computer. The central
processing unit is not hampered by the
microprocessors' ability to move data in and out of
computer memory. These safeguards frequently
result in a 99.8% or higher availability guarantee for
all crucial hardware operations.
In addition to hardware, fresh digital code for the
system's control can be created, tested, and put
online on the backup computer. Most of the time,
digital computers are used in fixed cycle operating
mode with priority interrupts, which causes them to
run a series of tasks on a recurring basis. The scan
cycle for the most important functions is the
quickest. The following categories are typically
scanned every two seconds:
Every status point, including the location of the
switchgear, the loads and voltages in the
substation, the tap positions of the transformers,
and the capacitor banks.
Schedules for interchanges and tie-line flow.
Lines’ capacity, operational restrictions, and
generator loads and voltage.
Telemetry verification to find errors and failures
in the distant bidirectional communication links
between the digital computer and remote
equipment.
Every 4 seconds, the turbine generators are
frequently instructed to operate at higher power
levels, with load adjustments dependent on each
unit's response capacity in MW/min. The computer,
while running an economic dispatch program,
adjusts the base power settings for each unit's
reaction capabilities every 5 minutes on average.
3 Power System State Estimation
The system states produced from unsophisticated
measurements in power systems are not precise
enough to be used for complex system operations
and online control due to the inherent flaws in
metering devices and communication networks.
This is why correct state estimation is a crucial
feature in power systems. Based on a collection of
real-time measurements, a state estimator (SE)
establishes the state of the system. There are three
kinds of real-time measurements that can be made
within the framework of a PSCC:
Examples of analog metrics are real and
reactive power flows over transmission
lines, real and reactive power injections, and
bus voltage magnitudes.
Switch and breaker state, as well as
transformer LTC positions, are measured
using logic.
Predicted bus loads and production are
examples of pseudo-measurements.
Telemetered readings of analog and logic are
sent to the PSCC. The statistics may contain noise
and errors. Data errors can be brought on by noisy
communication systems, malfunctioning measuring
and telemetry equipment, and delays in data
transmission. A system's state is described by a set
of variables that, at any given moment, contain all
the data necessary for us to fully predict how the
system will behave at time t. A practical decision is
to choose a small number of variables, designating a
small number of state variables that are adequate. It
should be noted that the state variables may not
always be easily available, quantifiable, or
observable. The system model used is built on a
nodal depiction, making the choice of the state
variables simple.
The voltage magnitudes and angles are the state
variables, while line impedances are assumed as
known. This follows because, once the state values
are known, all other values can be specified
uniquely. State estimation is a mathematical
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
61
Volume 18, 2023
procedure that generates a description of the power
system by computing the best estimation of the state
variables (bus voltages and angles) of the power
system based on the incorrect data that was
received.
Secondary quantities (like line flows) are easily
derivable once state variables are approximated. The
network configuration is established by the network
topology module after processing the logic data. In
addition to using data from the network parameters,
the configuration of the network provided by the
topology of the network, and occasionally pseudo
measurements, the state estimator processes the
collection of analog measurements to determine the
system state. Since it is not feasible to measure all
network parameters in-depth in the field, one-line
diagrams and manufacturer data are used to
calculate parameter values. This could then add
another potential error source.
The fundamental power system state estimator's
mathematical formulation assumes that the power
system has static behavior. Assume a system with n
state variables, represented by xi where i=1,...,n.
Suppose there are m measurements accessible. The
state vector is x, and the measurement vector is
indicated by the letter z. If the noise is v, then the
relation between measurements and states denoted
by h is given by:
󰇛󰇜 (1a)
or:
󰇛󰇜 (1b)
If h(x) is linearized, then:
 (2)
The measurement matrix, or H, is unaffected by
the state factors.
The goal is to find the best estimation of x,
denoted by . The weighted least squares (WLS)
idea is the foundation of the most widely used
method. The technique seeks to reduce the
differences between the related equations and the
measurements. To achieve this, the next
optimization function must be minimized:
 󰇛󰇜
󰇛󰇜 󰇛󰇜 (3a)
Where R is a diagonal matrix that has the
variances of the measurement error. (3a) can be
rewritten as:
󰇛󰇜󰇛 󰇛󰇜󰇜
(3b)
To have a minimum the following equation must be
fulfilled:
󰇛󰇜
 󰇛󰇜󰇟 󰇛󰇜󰇠 (4)
Where H(x) is the Jacobean measurement matrix
with m x n dimensions:
󰇛󰇜󰇛󰇜
 (5)
After h(x) is linearized:
󰇛 󰇜 󰇛󰇜  (6)
The following obtained:
󰇛󰇜 󰇟 󰇛󰇜󰇠 (7)
  (8)
The best estimations are found by applying the
equation below:


󰇟 󰇛󰇜󰇠 (9)
This means that a criterion of convergence
decides when the iteration is halted, and the state
variables are incrementally approximated to a value.
The measurements are related to one another
separately by the matrix W, also known as the
weighting matrix. The selection of W components
affects the outcomes. All measurements are of
identical quality if W=I is chosen.
4 Assessment of Steady State Stability
The analysis of steady-state stability goes far
beyond merely estimating the probability of
instability as small, gradual changes in load near the
maximal loadability limit. The steady-state stability
analysis calculates the separation from a system
state where voltages may collapse and units may
lose synchronism, regardless of the underlying
solution technique. This distance is measured using
a straightforward indicator called the steady-state
stability reserve. System-wide and for transmission
corridors with stability restrictions, the evaluation is
conducted.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
62
Volume 18, 2023
4.1 Steady-State Stability (Power and
Voltage Reserve Indicators)
The idea of steady-state stability reserve provides a
very simple way to express "how far" the present, or
actual, system state is from the "critical" state where
even a small change in the operating parameters
may result in steady-state instability. These are the
two categories of stable reserve indicators:
 
 󰇟󰇠 (10)
 
 󰇟󰇠 (11)
where:
: determines the stable
reserve's power capacity (in MW).
: determines the voltage
values for the stable reserve.
: is the total power (in MW) of the system’s
utilization, including generation and imports.
: is the power (in MW) in the actual (base)
case.
: is the average system voltage in the critical
case.
: is the voltage in the base case.
Maximum MW network utilization, also known
as maximum MW loadability, or the system
operating conditions just before the state of voltage
collapse is achieved by alternating steady-state
stability calculations that determine whether the
system is stable or unstable.
5 Dynamic Security Assessment (DSA)
The design of a DSA system enables the selection of
various load-flow situations and the construction of
individual contingencies for automatic evaluation.
User-defined parameters are used to evaluate the
contingencies. Figure 2 shows the procedure
graphically. Several user-selectable load-flow
scenarios are offered at the simulation level. The
most serious scenarios can be chosen and calculated
using the contingency builder. The software defines
the security criteria that can be combined to create
sets of standards characterizing the constraints of
the system and are appropriate for each user's
requirements. The DSA notifies and records the
events that result in system limit breaches, such as
unstable generators, voltages below 80%, angles
between nodes greater than 40°, and so on.
Fig. 2: The structure of the DSA system.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
63
Volume 18, 2023
These scenarios are very simple to recalculate,
and the analyst can see all the usual characteristics
to get a clearer understanding. The operator can also
keep track of the key contingencies concurrently.
One of a DSA system's primary design criteria
should be its capacity to:
Simulate key elements of active switching or
control equipment, such as capacitor banks and
FACTS devices, along with their control
mechanisms. These elements include lines,
cables, transformers, and other inactive grid
equipment.
When simulating cascading faults, depict the
essential protection's action.
When simulating contingencies, use a
straightforward method for building
contingencies.
6 Restoration Plan
6.1 General Guides after a Blackout
The ability to restore an Electric Power System after
any fault is critical to its operation. Many European
Transmission System Operators (TSOs) have
available online their restoration plans as the
Belgian TSO (ELIA), [43], or the Irish TSO
(EIRGRID), [44]. There have been plenty of
research works on the restoration process after a
blackout, [45], [46], [47]. The restoration process
can be divided into three stages: start-up of
generators, restoration of the transmission system,
and restoration of supply to consumers (loads).
After the start-up sequence of the generating units is
determined, it is very important to find the shortest
"path" to transfer the energy to the transmission
network, so that we have an immediate energy
supply to the network. In Table 1 the general guides
for restoration after a blackout are shown.
Table 1. General guides for restoration after a blackout for the dispatchers of a PSCC
Actions
Tools
Communication
Wind farm shutdown signal
Communication of the National Control Center with all the Regional
Control Centers, the Distribution System Operator (DSO), and TSOs
of neighboring countries
Landlines, Mobiles Phones, or other
communication systems each TSO has (e.g.,
power line carrier)
Status determination of Black Start (BS) and Non-Black (NBS) Start production units
Communication with Black Start units – setting time for black start
Relevant information must be referred to the
restoration plan of each regional control
center
Communicating with non-Black Start units, determining their status and
the critical time to restore power and restart time after power is
restored.
Priority of non- Black Start units for power supply
Division of the transmission system into subsystems
Division of the transmission system into subsystems
Use of the restoration plan as a guide and designing
dividing lines in the network plan.
Clear demarcation of the subsystems
Route selection from BS units to NBS units with priority
Estimation of the transmission system status
Studies, reports, and information from the Energy
Management System (EMS) that the TSO
uses
Collaboration with the TSOs to ensure that the route has the required
technical staff
Subsystem electrification and load supply
Subsystem electrification either using the bottom-up or the top-down
method
During the load supply, ensure that the frequency is high enough and the
voltage drop that will occur with the connection will not create very
low voltages
Priority of loads for reconnection in consultation
with the DSO
Synchronization of subsystems
Use synchronization points as defined in the restoration plan if possible.
Use of the restoration plan that each TSO has
issued
Providing instructions to the operators during the synchronization process
Completion of the restoration process
Gradual System’s restoration
EMS contingency analysis
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
64
Volume 18, 2023
Some important issues during a blackout are the
following:
The operators of black start power stations and
the substations must be authorized so that, if no
voltage is present, they will open all (external to
the station) breakers.
In thermal power plants, power to the auxiliary
machinery must be restored within a short
critical time to achieve a "warm restart".
The TSO must declare its status (Normal, Alert,
Emergency, or Blackout) to the EAS System,
informing this way all the other TSOs of
ENTSO-E.
The cooperation of TSOs, particularly those in
proximity, is a crucial factor during the repair
process. Typically, nearby TSOs must energize the
interconnection power lines after a blackout during
the top-down restoration process. The European
Awareness System (EAS) is also a helpful
instrument for communication between TSOs,
signalizing the rise of emergency situations and also
helping with system restoration. Distribution System
Operators (DSOs) are typically encouraged to
reduce loads before a major blackout and during the
TSOs' attempt to prevent it. The DSO's "strategy"
up to this point in the event of a blackout is to wait
for TSO restoration and increase loads while it is
happening. Cooperation between TSO, DSO, and
governmental organizations like the Police and the
Fire Brigade, should be guaranteed to reduce the
restoration time in a blackout, particularly if it has
been brought on by a natural catastrophe like flood,
earthquake, fire, etc.
6.2 Activation Strategies after a Blackout
There are two central principles that guide the
process of restoring the electricity system after a
blackout:
Bottom-up: Using Black Start units and/or house
load units with islanding capabilities, the affected
areas are recovered by self-reactivating the area in
chunks ready for resynchronization with another
area.
Top-down: Using interconnection links to
transfer energy from a safe system, a normally
isolated system with a serious disruption is revived
using external voltage sources. The interrupted TSO
must vouch for its commitment to adhering to the
limits of active and reactive power flows on the
interconnection lines set forth in bilateral
agreements.
The current practices across Europe are:
a. In the Baltic region, restoration plans are based
on the top-down principle.
b. In continental Europe and the Nordic regions,
both methodologies are used, considering the
existing situation (availability of Black Start
units and units in auxiliary feed mode within the
TSO's area of responsibility, duration of the two
principles, and the state of the voltage in the
neighboring network).
c. In Great Britain, the restoration plans are based
on the bottom-up principle.
d. In the Ireland / Northern Ireland region, once
the Black Start units start-up, the non-Black
Start target unit supply restoration routes will be
activated and initial load restoration will be
required to stabilize the restoration routes
(balancing the production with the demand).
The TSO determines the load restoration steps
required in terms of size and location and the
relevant DSO load coordinator will implement
them. Very good coordination between TSO and
DSO is required, especially in the early stages of
restoring stable operation and minimizing frequency
and voltage deviations.
For example, in Figure 3 the geographical
distribution of three separate subsystems (NW, NE,
S), during restoration in the Belgian TSO (ELIA),
using the bottom-up strategy is depicted, [43]. The
restoration plan defines that in case of a blackout, 4
black start units will be used for the formation of
these three separate regions.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
65
Volume 18, 2023
Fig. 3: Geographical distribution of 3 separate subsystems (NW, NE, S), during restoration in the Belgian TSO
using the bottom-up strategy.
6.3 Factors that May Affect the Restoration
Process
Although there is a restoration plan from every
TSO, very often there are some unpredictable
situations that may cause its modification during
restoration, [46]. In [47], an estimation method of
the probability of restoration or recovery time for
electric power systems is proposed. Common
problems that occur during a restoration process are:
Generators that lose their auxiliary loads may
not be able to remain in this state for long. In
many stations, it is not possible to close the high
voltage (HV) switch with a "dead busbar" so
that a subsystem cannot be formed from a single
generator.
According to restoration guidelines, all
substations must be isolated, which means that
all circuit breakers must be opened. However,
some high-voltage circuit breakers may not
have opened in time.
The mobile phone network will almost certainly
be congested and may even collapse due to a
national outage. A complete failure of all
communication systems is extremely unlikely.
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
66
Volume 18, 2023
Satellite phones must be installed at multiple
key locations, including all Black Start power
units and all Control Centers. If these phones
are the only available methods of
communication, recovery time will be
significantly longer.
Some electrical components of the Transmission
System (substations, power lines, etc.) may be
unavailable as planned in the restoration plan.
Uncontrollable parameters such as traffic chaos
and extreme weather conditions can
significantly delay the access of personnel to the
substations or the control centers on the day of
the incident.
7 Discussion
In this work, the role of a PSCC has been
analytically presented. The monitoring and control
of the grid through the PSCCs provide reliability
because it enables the operation of the grid even
closer to its limits. The PSCC is the “brain” of a
power system. It detects the power system's
condition, finds its state, plans its movement, and
offers protection from exogenous events. However,
the final decisions are taken by the personnel of the
PSCC known as dispatchers. Dispatchers are
electrical engineers, working in shifts to provide the
system’s balance and are the ones who will face the
great difficulty of a blackout. They should be
technically educated, and well-trained because the
importance of their job demands it.
This research work focuses also on the
importance of the dispatcher in a possible blackout.
The restoration plan as it was presented in section 6
will not be possible to be followed unless capable
and well-trained dispatchers know what to do in
such an event. Sometimes they have to unjust the
restoration plan, something that requires skills. The
software systems that a PSCC has are extremely
important for the operation of a power system and
cannot be done by humans. However, the restoration
process following the bottom-up or top-down
procedures needs dispatchers who will be able to
adjust it to the current power system’s conditions.
8 Conclusions
The crucial role of PSCCs in the optimum operation
of power systems and their significant role in power
system restoration have been discussed in this work.
However, they need improvements in their design
and operation. Here are a few things to think about
when designing control centers:
Many control centers that are unable to
communicate with one another cannot control a
single interconnected grid. It must be simple to
store and exchange data automatically and
continuously without relying on operator-to-
operator phone calls.
The monitoring systems must be standardized,
including the frequency of data collection, time
stamping, alarming, visualization, etc., to allow
dispatchers at various control centers located
throughout the grid to interact effectively.
More specificity is required in the control
reliability requirements. The same ones, like
voltage control, are less common even though
this has been done for frequency control.
The real-time data made accessible to operators
and control centers across the grid should be
chosen based on reliability requirements. The
current argument over whether certain data
belongs to generating firms as proprietary must
end when the grid's dependability is harmed.
If the above suggestions are adopted the operation
of the power systems via the control centers will be
significantly improved and the very known effects
of possible back out to the society and the economy
will be minimized.
References:
[1] G. P. Azevedo and A. L. Oliveira Filho,
“Control centers with open architectures,”
IEEE Comput. App. Power, Vol. 14, No. 4,
2001, pp. 27–32.
[2] G. P. Azevedo, B. Feijo, and M. Costa, FF
Wu, K Moslehi, A.Bose. “Power system
control centers: Past, present, and future,”
Proceedings of the IEEE, Vol.93, No.11,
2005, pp.1980-1908.
[3] F. Maghsoodlou, R. Masiello, and T. Ray,
“Energy management systems,” IEEE Power
Energy, Vol. 2, No. 5, 2004, pp. 49–57.
[4] Meles, T.H. Impact of power outages on
households in developing countries: Evidence
from Ethiopia. Energy Econ. Vol 91, 2020,
104882.
[5] Shivakumar, A.; Welsch, M.; Taliotis, C.;
Jakšić, D.; Baričević, T.; Howells, M.; Gupta,
S.; Rogner, H. Valuing blackouts and lost
leisure: Estimating electricity interruption
costs for households across the European
Union. Energy Res. Soc. Sci. 2017, Vol. 34,
pp. 39–48.
[6] Haes Alhelou, H.; Hamedani-Golshan, M.E.;
Njenda, T.C.; Siano, P. A Survey on Power
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
67
Volume 18, 2023
System Blackout and Cascading Events:
Research Motivations and Challenges.
Energies, Vol. 12, 2019, 682.
[7] Andersson, G.; Donalek, P.; Farmer, R.;
Hatziargyriou, N.; Kamwa, I.; Kundur, P.;
Martins, N.; Paserba, J.; Pourbeik, P.;
Sanchez-Gasca, J.; et al. Causes of the 2003
major grid blackouts in North America and
Europe, and recommended means to improve
system dynamic performance. IEEE Trans.
Power Syst. Vol. 20, 2005, pp. 1922–1928.
[8] Sambhi S., Sharma H., Kumar P., Fotis G.,
Vita V., Ekonomou L. Techno-Economic
Optimization of an Off-Grid Hybrid Power
Generation for SRM IST, Delhi-NCR
Campus. Energies 2022, Vol. 15, No. 21,
7880. https://doi.org/10.3390/en15217880
[9] Sambhi, S., Sharma, H., Bhadoria, V., Kumar,
P., Chaurasia, R., Chaurasia, G.S., Fotis, G.,
Vita, V., Ekonomou, L., Pavlatos, C.
Economic Feasibility of a Renewable
Integrated Hybrid Power Generation System
for a Rural Village of Ladakh. Energies, Vol.
15, No 23, 2022, 9126.
https://doi.org/10.3390/en15239126
[10] Sambhi, S., Sharma, H., Bhadoria, V., Kumar,
P., Chaurasia, R., Fotis, G., Vita, V. Technical
and Economic Analysis of Solar PV/Diesel
Generator Smart Hybrid Power Plant Using
Different Battery Storage Technologies for
SRM IST, Delhi-NCR Campus.
Sustainability, Vol. 15, No. 14, 2023, 3666.
https://doi.org/10.3390/su15043666
[11] Ekonomou, L., Fotis, G., Vita, V. and
Mladenov, V., Distributed Generation
Islanding Effect on Distribution Networks and
End User Loads Using the Master-Slave
Islanding Method. Journal of Power and
Energy Engineering, Vol. 4, 2016, pp. 1-24.
http://dx.doi.org/10.4236/jpee.2016.410001
[12] Fotis G., Dikeakos C., Zafeiropoulos E.,
Pappas S., Vita V., Scalability and
Replicability for Smart Grid Innovation
Projects and the Improvement of Renewable
Energy Sources Exploitation: The
FLEXITRANSTORE Case. Energies, Vol.
15, No. 13, 2022.
https://doi.org/10.3390/en15134519
[13] Zafeiropoulou M., Mentis I., Sijakovic N.,
Terzic A., Fotis, G., Maris, T.I., Vita, V.,
Zoulias E., Ristic V., Ekonomou, L.,
Forecasting Transmission and Distribution
System Flexibility Needs for Severe Weather
Condition Resilience and Outage
Management. Applied Sciences, Vol. 12, No.
14, 2022.
https://doi.org/10.3390/app12147334
[14] Sijakovic N., Terzic A., Fotis G., Mentis I.,
Zafeiropoulou M., Maris T.I., Zoulias E.,
Elias C., Ristic V., Vita V. Active System
Management Approach for Flexibility
Services to the Greek Transmission and
Distribution System. Energies 2022, Vol. 15,
No.17, 6134.
https://doi.org/10.3390/en15176134
[15] Fotis, G., Vita, V., Maris, T.I. Risks in the
European Transmission System and a Novel
Restoration Strategy for a Power System after
a Major Blackout. Applied Sciences, 2023,
Vol. 13, No. 1, 83.
https://doi.org/10.3390/app13010083
[16] Vita, V., Fotis, G., Pavlatos, C., Mladenov, V.
A New Restoration Strategy in Microgrids
after a Blackout with Priority in Critical
Loads. Sustainability 2023, Vol. 15, No. 3,
1974. https://doi.org/10.3390/su15031974
[17] Adewumi O.B., Fotis G., Vita V., Nankoo
D., Ekonomou L., The Impact of Distributed
Energy Storage on Distribution and
Transmission Networks’ Power Quality.
Applied Sciences, Vol. 12, No. 13, 2022.
https://doi.org/10.3390/app12136466
[18] Kourtesi St., Ekonomou L., Nakulas A.,
Fotis G., Zoulias E., Modeling and
simulation of a single phase photovoltaic
inverter and investigation of switching
strategies for harmonic minimization. 6th
WSEAS Int.Conf. on Applications of
Electrical Engineering (AEE '07), Istanbul,
Turkey, May 27-29, ΠΠ. 155-159, 2007.
[19] J. H. Jo, M. R. Aldeman, and D. G. Loomis,
‘‘Optimum penetration of regional utility-
scale renewable energy systems,’’ Renew.
Energy, Vol. 118, 2018, pp. 328–334.
[20] A. Zerrahn and W.-P. Schill, ‘‘Long-run
power storage requirements for high shares
of renewables: Review and a new model,’’
Renew. Sustain. Energy Rev., Vol. 79, 2017,
pp. 1518–1534.
[21] F. Cebulla, T. Naegler, and M. Pohl,
‘‘Electrical energy storage in highly
renewable European energy systems:
Capacity requirements, spatial distribution,
and storage dispatch,’’ J. Energy Storage,
vol. 14, 2017, pp. 211–223.
[22] European Network of Transmission System
Operators for Electricity (ENTSO-E), "P1
Policy 1: Load-Frequency Control and
Performance [C]", Available online:
https://eepublicdownloads.entsoe.eu/clean-
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
68
Volume 18, 2023
documents/pre2015/publications/ce/oh/Policy
1_final.pdf
[23] European Network of Transmission System
Operators for Electricity (ENTSO-E). P2
Policy 2: Scheduling and Accounting.
Available online
https://eepublicdownloads.entsoe.eu/clean-
documents/pre2015/publications/entsoe/Opera
tion_Handbook/Policy_2_final.pdf
[24] European Network of Transmission System
Operators for Electricity (ENTSO-E). P3
Policy 3: Operational Security. Available
online:
https://eepublicdownloads.entsoe.eu/clean-
documents/pre2015/publications/entsoe/Opera
tion_Handbook/Policy_3_final.pdf
[25] European Network of Transmission System
Operators for Electricity (ENTSO-E). P4 -
Policy 4: Coordinated Operational. Available
online:
https://eepublicdownloads.entsoe.eu/clean-
documents/pre2015/publications/entsoe/Opera
tion_Handbook/Policy-4-v2.pdf
[26] European Network of Transmission System
Operators for Electricity (ENTSO-E). P5
Policy 5: Emergency Operations. Available
online:
https://eepublicdownloads.entsoe.eu/clean-
documents/pre2015/publications/entsoe/Opera
tion_Handbook/Policy_5_final.pdf
[27] European Network of Transmission System
Operators for Electricity (ENTSO-E). P6
Policy 6: Communication Infrastructure.
Available online:
https://eepublicdownloads.entsoe.eu/clean-
documents/pre2015/publications/entsoe/Opera
tion_Handbook/Policy_6_final.pdf
[28] European Network of Transmission System
Operators for Electricity (ENTSO-E). P7
Policy 7: Data Exchanges. Available online:
https://gordoncheng.files.wordpress.com/2010
/08/policy_7_final-
e8b387e69699e4baa4e68f9b.pdf
[29] European Network of Transmission System
Operators for Electricity (ENTSO-E). P8
Policy 8: Operational Training. Available
online:
https://gordoncheng.files.wordpress.com/201
0/08/policy_8_final-
e8aabfe5baa6e9818be8bd89e8a893e7b7b4.p
df
[30] Adibi, M. M. Power System Restoration:
Methodologies and Implementation Strategies
Wiley-IEEE Press; 1st edition, June 22, 2000.
[31] Wang, H.T.; Liu, Y.T. Multi-objective
optimization of power system reconstruction
based on NSGA-II Autom Electr Power Syst,
Vol. 33, 2009, pp. 14–18.
[32] Iman, S.; Abbas, K.; Rene, F. The study of
switching overvoltages under power system
restoration scenario using extended delta-bar-
delta algorithm. Int J Emerg Electr Power
Syst, Vol. 14, 2013, pp. 219–230.
[33] Liu, W.J.; Lin, Z.Z.; Wen, F.S. et al
Intuitionistic fuzzy Choquet integral operator-
based approach for black-start decision-
making. IET Generation Transmission and
Distribution, Vol. 6, 2012, pp. 378–386.
[34] Ye, D.Y.; Zhang, M.J.; Sutanto, D. A hybrid
multiagent framework with Q-learning for
power grid systems restoration. IEEE
Transactions on Power Systems, Vol. 26,
2011, pp. 2434–2441.
[35] Ren, F.H.; Zhang, M.J.; Soetanto, D. et al
Conceptual design of a multi-agent system for
interconnected power systems restoration
IEEE Transactions on Power Systems, Vol.
27, 2012, pp. 732–740.
[36] Wang, H.T., Liu, Y.T., Qiu, X.Z. et al Multi-
agent based on Stackelberg decision for power
system restoration. Autom Electr Power Syst,
Vol. 30 2006, pp. 5–9.
[37] Xu, Y.L.; Liu, W.X. Novel multiagent based
load restoration algorithm for microgrids.
IEEE Trans Smart Grid, Vol. 2, 2011, pp.
152–161.
[38] Hou, Y.H.; Liu, C.C.; Sun, K. et al
Computation of milestones for decision
support during system restoration. IEEE
Transactions on Power Systems, Vol. 26,
2011pp. 1399–1409.
[39] D. Marihart, “Communications Technology
Guidelines for EMS/SCADA Systems,” IEEE
Transactions on Power Delivery, Vol. 16, No.
2, 2001, pp. 181-188.
[40] Monticelli, State Estimation in Electric Power
Systems, A Generalized Approach, Kluwer,
Boston, 1999.
[41] Moser, G. Ejebe, J. Frame, “Network and
Power Applications for EMS within a
Competitive Environment, Proceedings of
the IEEE Power Engineering Society
Transmission and Distribution Conference,
1999, pp. 280-285.
[42] Gonzalez-Perez, “Information Systems
Supporting Electric Energy Deregulation in
North America,” presentation at the 2002
IEEE Summer Meeting, Chicago, July 2002,
WSEAS TRANSACTIONS on POWER SYSTEMS
DOI: 10.37394/232016.2023.18.7
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
69
Volume 18, 2023
with permission from Open Access
Technology, Incorporated.
[43] ELIA Belgium’s Transmission System
Operator. Design note on restoration services.
20 December 2018. Available online:
https://www.elia.be/-/media/project/elia/elia-
site/electricity-market-and-system---
document-library/restoration-services---rsp-
and-emergency-situations/2018/2018-design-
note---future-restoration-services.pdf
(Accessed on 20 September 2022).
[44] EIRGRID Irish Transmission System
Operator. Design of the System Restoration
Plan for Ireland. 16 October 2020. Available
online: https://www.eirgridgroup.com/site-
files/library/EirGrid/EirGrid_System_Restorat
ion_Plan_Ireland.pdf.
[45] Liu, Y.; Fan, R.; Terzija, V. Power system
restoration: a literature review from 2006 to
2016. J. Mod. Power Syst. Clean Energy,
2016, 4, pp. 332–341.
https://doi.org/10.1007/s40565-016-0219-2
[46] Sidhu, T. S. et al. Protection issues during
system restoration. IEEE Transactions on
Power Delivery, Vol. 20, 2005, pp. 47-56.
doi: 10.1109/TPWRD.2004.839734.
[47] Duffey, R. B.; Ha T. The Probability and
Timing of Power System Restoration. IEEE
Transactions on Power Systems, Vol. 28,
2013, pp. 3-9. doi:
10.1109/TPWRS.2012.2203832.
Contribution of Individual Authors to the
Creation of a Scientific Article (Ghostwriting
Policy)
The authors equally contributed in the present
research, at all stages from the formulation of the
problem to the final findings and solution.
Sources of Funding for Research Presented in a
Scientific Article or Scientific Article Itself
No funding was received for conducting this study.
Conflict of Interest
The authors have no conflict of interest to declare
that is relevant to the content of this article.
Creative Commons Attribution License 4.0
(Attribution 4.0 International, CC BY 4.0)
This article is published under the terms of the
Creative Commons Attribution License 4.0
https://creativecommons.org/licenses/by/4.0/deed.en
_US
Georgios Fotis, Christos Pavlatos, Vasiliki Vita
E-ISSN: 2224-350X
70
Volume 18, 2023