Steps for the Realization of a Medium-power Photovoltaic Park
SORIN IOAN DEACONU1, MARCEL TOPOR1, ALEXANDRU MIHAI BLAJ2, FEIFEI BU3
1Electrical Engineering and Industrial Informatics Department, Politechnica University of Timisoara,
Timisoara, ROMANIA
2College of Engineering, Al Asal University, Dammam, SAUDI ARABIA
3Nanjing University of Aeronautics and Astronautics, Nanjing, CHINA
Abstract: - The design of photovoltaic parks has become in Romania, now, one of the most profitable and safe
investments in the field of renewable energy sources, not only at present, but even more so in the future. Solar
photovoltaic parks are favored by maximum exposure to solar radiation, a minimal impact on the environment,
allowing the production of energy with a cost per kWp lower than that of other installations. The execution period
of a photovoltaic park varies between 3-6 months depending on location and weather conditions. Romania has a
high degree of solar radiation, suitable for investment in photovoltaic parks. There are three categories of documents
required for the establishment of a photovoltaic park: those related of the land on which the park is build, the solution
study for obtaining the technical approval for connection (ATR) to the electrical grid and obtaining the
establishment authorization. The realization costs involved in building and designing a photovoltaic park are
between 1.1-1.9 Euro/Watt. The quality of the equipment used in construction, the shape of the land, the costs of
connection to the national electrical grid, are factors that can constitute the cost of realization. Another important
factor in terms of income is the level of operational expenses, which is between 2% and 8% of the annual income
and includes security, equipment and land maintenance, system monitoring. The paper will present a technical and
economic calculation for a photovoltaic park with a power of 400 kW.
Keywords: -photovoltaic park, irradiation and solar electricity potential, green certificate, RETScreen Expert
Software
Received: October 7, 2023. Revised: August 16, 2024. Accepted: September 7, 2024. Published: October 7, 2024.
1. Introduction
Numerous countries and regions have incorporated
substantial solar energy capacity into their electricity
grids to complement or provide an alternative to
traditional energy sources. Solar power facilities utilize
one of two technologies: photovoltaic (PV) systems,
which employ solar panels placed on rooftops or in
ground-based solar farms to directly convert sunlight
into electrical power, and concentrated solar power
(CSP, also known as "concentrated solar thermal")
plants, which harness solar thermal energy to produce
steam, subsequently transformed into electricity using a
turbine [1], [2]. The global expansion of photovoltaics
exhibits significant dynamism and varies considerably
from one country to another. As of the conclusion of
2019, a cumulative total of 629 GW of solar power had
been installed worldwide [3]. By early 2020, China led
the world in solar power capacity with 208 GW [4], [5],
constituting one-third of the global solar energy
capacity. In 2020, at least 37 countries across the globe
had a cumulative PV capacity exceeding one gigawatt.
The prominent solar power installers from 2016 to 2019
were China, the United States, and India. The first 10
countries in photovoltaics industry, [4-7], are presented
in figure 1.
Fig. 1. The first 10 countries in photovoltaics industry
in 2021
In Romania, there are more and more solar power
plants based on photovoltaic panels and a tripling of the
photovoltaic capacity is expected, until the year 2030,
when coal-based energy will be almost completely
eliminated - shows a Global Data report, which
estimates that, in the next 8 years, Romania will have a
International Journal of Electrical Engineering and Computer Science
DOI: 10.37394/232027.2024.6.16
Sorin Ioan Deaconu,
Marcel Topor, Alexandru Mihai Blaj, Feifei Bu
E-ISSN: 2769-2507
137
Volume 6, 2024
photovoltaic capacity of 4250 MW, compared to the
1400 MW it currently has [8].
Speaking of the advantages of solar panels, the list is
quite comprehensive. First, the energy produced is free.
Lighting and heating the house or domestic water will
have very low costs. Depending on the size of the
photovoltaic system used, the savings on electricity bills
can be very large. Moreover, if the system generates
more energy than you can consume and you are
connected to the electricity grid, the surplus can be
exported and you will be rewarded for it. Secondly, solar
panels are easy to mount and maintain. They can be
placed on the roof of the house or even on open fields.
They have an extended lifespan, over 20 years, and their
maintenance is not complicated at all. In addition, the
components that deteriorate or break over time can be
replaced very easily. The inverter has a somewhat
shorter lifespan, between 5 and 10 years, because it
works continuously. The other elements used for
connections and cables can also deteriorate over time,
but they can be easily replaced. Finally yet importantly,
another great advantage of photovoltaic panels and
systems is the reduction of pollution. Because they use
an inexhaustible resource, such as sunlight, they are
considered the friendliest solutions for the environment.
Classic fuels, such as gas or coal, with the help of which
electricity is obtained, are increasingly limited, more
expensive and more polluting resources [9].
On-grid photovoltaic systems require some essential
conditions for a good operation, related to the national
electrical grid to which it is connected. Thus, an on-grid
photovoltaic system, even if it represents an electrical
energy production unit, implies a permanent connection
to the electrical grid, like an ordinary consumer.
However, unlike consumers, the connection to the
network of an on-grid photovoltaic system is used in
order to deliver the surplus energy produced by it. The
national electricity grid takes the place of a battery in an
off-grid type system. This brings both advantages and
disadvantages. The main advantage is the significantly
lower cost of a system that does not involve batteries.
Another advantage is the lack of risks associated with
larger capacity batteries, such as the risk of explosion,
overheating, low performance in different weather
conditions, etc. In addition, an accumulator has a limited
storage capacity, and if the energy in it is not consumed,
the production potential of the panels is lost. However,
there are disadvantages related to connecting a
photovoltaic system to the national electricity grid. The
main disadvantage is related to the fact that the voltage
in the electricity grid differs greatly depending on the
area. The causes that lead to the appearance of voltages
over 240V are: the location of the house where the
photovoltaic system is mounted relatively close to the
transformer station, several photovoltaic systems
installed on the same street mean, on the one hand, a
source of clean energy, but in the absence of
consumption, they negatively influence the level of
electrical voltage in the grid, another reason for the
increase in voltage may not be related to the power lines
of the national grid but to the cable used by the final
customers, respectively the cable between the output of
the bidirectional meter and the input to the general
electrical panel of each customer; if the section of this
cable is too small, the voltage drop will be greater and
then the inverter is forced to increase the voltage level
more than it would normally be in order to inject the
voltage into the grid, and last but not least, there are
specific problems because the electrical network
infrastructure is precarious and where there are problems
even without photovoltaic installations, and adding them
only worsens the already existing situation [9-16].
2. Project Location, Irradiation and
Solar Electricity Potential
Optimal sun exposure and minimal environmental
impact make photovoltaic parks an attractive energy
source, with profitability hinging on factors like income-
to-construction costs ratio. Primary revenue sources
include energy sales and green certificate trading.
Fig. 2. The location and the corresponding climatic
data
The green certificate signifies the production of
1MWh of renewable electricity. These purchased
certificates cover the obligatory renewable energy
portion in total consumer supply, determined annually
by ANRE. They remain valid for 16 months. The
Environmental Fund Authority imposes a 110 euro fine
per unpurchased certificate on non-compliant suppliers
and producers. Solar energy producers (comprising
power plants and photovoltaic parks) receive six green
certificates per 1MWh of delivered electricity.
Presently, a green certificate's maximum market value is
50 euros.
The project is situated near Geoagiu Bai town, with
a southern orientation. Figure 2 depicts the location and
International Journal of Electrical Engineering and Computer Science
DOI: 10.37394/232027.2024.6.16
Sorin Ioan Deaconu,
Marcel Topor, Alexandru Mihai Blaj, Feifei Bu
E-ISSN: 2769-2507
138
Volume 6, 2024
associated climatic data, while figure 3 illustrates daily
solar radiation and temperature. A 20 kV medium
voltage electric line traverses the area.
Fig. 3. Daily solar radiation and temperature in the
location of the project
3. Categories of Documents Required
for the Establishment of a Photovoltaic
Park and the Steps Required Becoming
a Prosumer
There are three categories of documents required for
the establishment of a photovoltaic park: those related to
the land on which the park is built, the solution study for
obtaining the technical approval for connection (ATR)
to the electrical grid and obtaining the establishment
authorization [13].
The first category includes the deed of sale, purchase
of the land, concession or lease, then the zonal urban
plan (PUZ) if the land is removed from the agricultural
circuit, the urban planning certificate (with the approvals
requested by it) and the opportunity study for the
evacuation of the power in the existing grid [13].
The second category includes the technical
documentation for the construction authorization
(DTAC), obtaining the construction authorization, the
technical project that starts with the DTAC and the
technical project for the power evacuation in the grid
[14].
The third category of documents involves obtaining
the ATR, then obtaining the establishment authorization
(given by ANRE), obtaining the commercial
exploitation license, registration on the regulated
electricity market (OPCOM) with (accreditation for
green energy), obtaining the Transelectrica approval for
the transport of electricity, if the connection is made
directly to their grids [15].
If you produce electricity from renewable sources and,
apart from your own consumption, but not necessarily
deliver the surplus electricity to the national electricity
distribution network, this means that you can become a
prosumer. The regulatory authority in the field (ANRE)
monitors the evolution of prosumers based on data and
information collected monthly from distribution operators.
The distribution operators have duties regarding the
connection to the electricity grid, the certification of the
prosumer quality, the measurement of the electricity
consumed/injected from/into the grid and the transmission
of information to the supplier in order to bill the electricity.
In order to become a prosumer, you must go through
several necessary steps: a connection request is
submitted to the electricity distributor; following the
submitted request, a connection solution is established
and the technical connection approval (ATR) is received
from the distribution operator; the connection contract is
signed; the system of photovoltaic panels with an
installed power of no more than 400 kW per place of
consumption is installed by specialized personnel; the
file of the usage facility and the request to energize the
usage facility for tests are submitted to the electricity
distributor; the report of receipt of commissioning of the
user facility is sent, after tests, to the electricity
distributor; it receives the connection certificate from the
distribution operator and the prosumer certification; a
sale-purchase contract for the electricity produced and
delivered in the grid is signed with the electricity
supplier [10].
If it is not necessary to change the connection
solution for the installation of the photovoltaic panel
system at the place of consumption, then the notification
regarding the connection to the existing place of
consumption of the photovoltaic panel system is sent to
the distribution operator, after its installation. In this
case, the distribution operator updates the existing
connection certificate without the need to issue the
technical connection approval [11].
4. Using the RETscreen Expert
Software for Design and Economic
Assessment
RETScreen is a Clean Energy Management Software
system designed for assessing the feasibility of energy
efficiency, renewable energy, and cogeneration projects,
encompassing power, heating, and cooling. It empowers
professionals and decision-makers to swiftly evaluate
the technical and financial viability of potential clean
energy projects, aiding in decision-making. This
software platform also simplifies performance
measurement and verification for facilities while
identifying additional energy savings and production
opportunities. RETScreen stands as the most
comprehensive tool of its kind, enabling engineers,
architects, and financial planners to model and analyze
a wide range of clean energy projects. Decision-makers
can conduct a five step standard analysis, including
energy analysis, cost analysis, emission analysis,
financial analysis, and sensitivity/risk analysis. Fully
integrated into these analytical tools are benchmark,
product, project, hydrology and climate databases (the
International Journal of Electrical Engineering and Computer Science
DOI: 10.37394/232027.2024.6.16
Sorin Ioan Deaconu,
Marcel Topor, Alexandru Mihai Blaj, Feifei Bu
E-ISSN: 2769-2507
139
Volume 6, 2024
latter with 6,700 ground-station locations plus NASA
satellite data covering the entire surface of the planet),
as well as links to worldwide energy resource maps.
Moreover, to help the user rapidly commence analysis,
RETScreen has built in an extensive database of generic
clean energy project templates [17].
We will divide the park into four modules with equal
power of 100 kW each. We will do the analysis with the
RETScreen program for one module and then generalize
the conclusions for all four modules. Figure 4 shows
information about a module of the facility and Figure 5
shows the production cost in Canadian dollars of energy,
compared to other types of power plants.
Fig. 4. Information about a module of the facility
Fig. 5. The production cost in Canadian dollars of
energy, compared to other types of power plants
It is observed that for a photovoltaic park with fixed
panels the cost of electricity production is 0.05 CAD =
0.044 USD = 0.199 RON / kWh. The following figures
(6, 7, 8, 9, and 10) show the results of the analysis with
the RETScreen program for a 100 kW module of the
fixed photovoltaic park.
Fig. 6. Energy calculation data power plants
Fig. 7. The proceeds from the energy produced, the
annual costs and the investment recovery period without
green certificates
Fig. 8. The receipts from green certificates, the initial
cost and the annual cost
International Journal of Electrical Engineering and Computer Science
DOI: 10.37394/232027.2024.6.16
Sorin Ioan Deaconu,
Marcel Topor, Alexandru Mihai Blaj, Feifei Bu
E-ISSN: 2769-2507
140
Volume 6, 2024
Fig. 9. Emission Analysis
Fig. 10. The final values of the analysis
Equipment chosen for execution: The photovoltaic
panels used are of the Canadian Solar monocrystalline
type, with an efficiency of 19% and a power of 320 W.
1248 panels are used. The MPPT type regulators are
from Victron type MPPT150/70. 100 such regulators are
used for the entire park. The inverters used are
HUAWEI-SUN 200-50 KTL-M3 three-phase with a
power of 50 kW. In total, there are 8 such inverters.
5. Conclusions
With the data corresponding to the chosen location,
the annual electricity production of a 100 kW module is
136 MWh. An average cost of 1900 CAD / kW was
chosen, resulting in a total investment cost of 758784
CAD. For the electricity produced, an average price of
0.15 CAD / kWh = 0.12 USD / kWh = 0.54 RON / kWh
was chosen. It results in an amount of 20427 CAD
collected per year for one module, respectively 84708
CAD for the entire photovoltaic park. If the green
certificates are not taken into account, the annual park
maintenance cost of 9984 CAD and the payment of the
loan in the amount of 58316 CAD per year (for 15
years), the investment recovery period is 10.6 years. If
we take into account the green certificates at a market
price of 34 CAD, 3264 certificates will be collected
annually for the whole park, which gives us an annual
income of 144240 CAD. In this situation, the investment
recovery period is 4.1 years.
References
[1] X. Yang, Y. H. Song and G. H. Wang A
comprehensive review on the development of
sustainable energy strategy and implementation in
China”, IEEE Transactions on Sustainable Energy,
2010, 1 (2) pp. 57-65.
[2] X. H. Ran and S. H. Miao, “Three-phase
probabilistic load flow for power system with
correlated wind, photovoltaic and load”, IET
Generation, Transmission & Distribution, 2016,10
(12) pp 3093-3101.
[3] M. Zeraati, M. E. H. Golshan and J. M. Guerrero,
“Voltage quality improvement in low voltage
distribution networks using reactive power
capability of single-phase PV inverters”, 2019,
IEEE Transactions on Smart Grid 10 (5) pp. 5057-
5065.
[4] J. Krata and T. K. Saha, “Real-time coordinated
voltage support with battery energy storage in a
distribution grid equipped with medium-scale PV
generation”, 2019, IEEE Transactions on Smart
Grid, 10 (3) pp. 3486-3497.
[5] A. Woyte, V. V. Thong and R. Belmans, “Voltage
fluctuations on distribution level introduced by
photovoltaic systems”, 2006, IEEE Transactions on
Energy Conversion, 21 (1) pp. 202-209.
[6] A. Jahid, S. Islam and S. Hossain, “Toward energy
efficiency aware renewable energy management in
green cellular networks with joint coordination”,
2019, IEEE Access, 7, pp. 75782-75797.
[7] J. S. Sara Oliveira-Pinto, “Assessment of the
potential of different floating solar technologies -
Overview and analysis of different case studies”,
Equinor 2020, ASA (Formerly Designated Statoil).
[8] H. Z. Müllejans, State-of-the-art for assessment of
solar energy technologies, 2020, European
Commission
[9] *** SR EN 50160:2011 Characteristics of voltage
in electrical distribution grids
[10] *** SR HD 472 S1:2002 and SR HD 472
S1:2002/A1:2002 Nominal voltages of low-voltage
public distribution grids
[11] *** SR CEI 61836:2006 Solar energy photovoltaic
conversion systems. Terms and symbols
[12] ***SR EN 62446:2010 Photovoltaic systems
connected to the grid. Minimum requirements for
system documentation, commissioning and
inspection
[13] *** SR CEI/TS 62257-6:2010 Recommendations
for low power renewable and hybrid energy
systems for rural electrification. Part 6: Reception,
operation, maintenance and replacement
[14] *** SR EN 61724 (CEI 61724):2006 Monitoring
the functioning qualities of photovoltaic systems.
Recommendations for data measurement, transfer
and analysis
International Journal of Electrical Engineering and Computer Science
DOI: 10.37394/232027.2024.6.16
Sorin Ioan Deaconu,
Marcel Topor, Alexandru Mihai Blaj, Feifei Bu
E-ISSN: 2769-2507
141
Volume 6, 2024
[15] *** SR CEI/TS 62257-7-1 Recommendations for
low power renewable and hybrid energy systems
for rural electrification. Part 7-1: Generators -
Photovoltaic panels
[16] *** SR EN 50438:2008 Prescriptions for
connecting micro generators in parallel with public
low voltage distribution grids
[17] *** RETScreen Clean Energy Management
Software, RETScreen Expert Version 9.0.1.94,
Minister of Natural Resources Canada 1997-2023
Contribution of Individual Authors to the
Creation of a Scientific Article (Ghostwriting
Policy)
The authors equally contributed in the present
research, at all stages from the formulation of the
problem to the final findings and solution.
Sources of Funding for Research Presented in a
Scientific Article or Scientific Article Itself
No funding was received for conducting this study.
Conflict of Interest
The authors have no conflicts of interest to declare
that are relevant to the content of this article.
Creative Commons Attribution License 4.0
(Attribution 4.0 International, CC BY 4.0)
This article is published under the terms of the
Creative Commons Attribution License 4.0
https://creativecommons.org/licenses/by/4.0/deed.en
_US
International Journal of Electrical Engineering and Computer Science
DOI: 10.37394/232027.2024.6.16
Sorin Ioan Deaconu,
Marcel Topor, Alexandru Mihai Blaj, Feifei Bu
E-ISSN: 2769-2507
142
Volume 6, 2024