Macro-engineering Design for an Artificial Lake in
Southeastern Jordan
OSAMA M. AL-HABAHBEH1, ROMIL S. AL-ADWAN1, MUSTAFA A. AL-KHAWALDEH2
1Mechatronics Engineering Department, The University of Jordan, Amman 11942, JORDAN
2Mechatronics Engineering Department, Philadelphia University, Amman-Jarash Road, JORDAN
Abstract: - Water situation in Jordan has become very critical. A feasible solution is to desalinate water drawn
from Gulf of Aqaba (GoA). Another problem that Jordan faces is the very short coastline. These two problems
can be solved by developing an artificial lake in south Jordan. The water from the lake can be desalinated while
the lake itself provides a badly needed coastline. This work presents a macro-engineering design for the
proposed lake; The proposed project is named "Red Sea-Jafer Basin Conduit (RSJBC)"; it involves a pipeline
connecting GoA at the Red Sea with Jafer Basin (JB) in the south-eastern desert, where the topography of the
region is exploited to develop an artificial Lake. Using multiple pumping stations, seawater will be pumped
from GoA to JB though a 220 km long pipeline. After constructing the project, it will take three years to fill-up
the Lake. Once it is filled, the pumping rate is reduced from 51 to 30 m3/s. However, based on fresh water
needs, a volume of up to 21 m3/s can be desalinated. The suggested pipeline route has a curved path (CP) to
avoid the mountains if it were to go straight path (SP). A comparison is conducted between CP and SP, where it
was found that CP offers the lowest development cost for RSJBC, given fabric pipe is used. More specifically,
a pipe diameter of 6 m enables total development cost of 2.74 B$, with corresponding annual operating cost of
306 M$.
Key-Words: - Artificial Lake, Jordan desert, Gulf of Aqaba, Jafer Basin, Water transport, Pumping station,
Gravity flow, Seawater pipeline, Seawater pumping, Tourist attraction development.
Received: July 18, 2021. Revised: May 13, 2022. Accepted: June 4, 2022. Published: June 21, 2022.
1 Introduction
One of the major challenges facing Jordan is the
insufficient water resources. A clear solution for this
problem is desalination of seawater brought from
GoA at the Red Sea. Another major challenge is the
very short coastline, as it hinders the potential for
growth of domestic tourism. These two challenges
together can be overcome using Macro-engineering
method, which is defined as the implementation of
very large-scale engineering designs. This method is
used to develop a design for an artificial lake in
south Jordan, where part of the water from the lake
can be desalinated and transported to cities, while
the lake itself provides Jordan with extra coastline.
The proposed design exploits JB, which is a unique
but overlooked natural resource that contributes
very little to the national economy. However, if the
basin is converted into a lake, it will become a tool
to attract investors, where many activities can be
done to generate revenue. The cost of the project
includes seawater pumping from GoA to JB as well
as pipes and installation. The total cost of
construction and operation will be estimated.
Large-scale water projects are important
infrastructure elements. Since antiquity, these
projects have been vital for development; Megdiche
et al. [1] highlighted seven examples of historic
hydraulic structures. Al-Saqarat et al. [2] indicated
that a network of freshwater sites in Jordan had been
visited by early humans. On the other hand, natural
rivers and lakes are the main sources of fresh
surface water. Therefore, they have received
considerable attention in the literature; Bonacci et
al. [3] studied the fluctuations in water levels at
Baćina Lakes. Goodwin et al. [4] investigated the
formation of Lakes in Antarctica from Ocean flood
events. Lukman et al. [5] studied the pollution in
Lake Toba in Indonesia. Abd Aziz et al. [6]
identified water contamination in Cempaka Lake.
The phenomenon of inter-basin water transfers was
studied by Gupta and Zaag [7]. The restored
ecosystem of Chilika lake in India was studied by
Mohanty et al. [8]. Badescu and Cathcart [9]
proposed a macro-engineering solution to raise the
Aral Sea level by importing water from Caspian
Sea. Stone [10] discussed the hydrolofical collapse
of Lake Urmia in Iran.
Many water transport studies have been
presented in the literature; an artificial lake design
was presented by Badescu et al. [11]; where they
proposed to bring seawater to lake Eyre in South
Australia. In an effort to solve the sand dunes
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
825
Volume 18, 2022
problem in the African desert, Badescu et al. [12]
suggested conveying seawater from the ocean to the
desert to fix the dunes by spraying them with water.
Gomaa et al. [13] evaluated the degree to which
pumping wells at Moghra aquifer in the Egypt
western desert will attract seawater to the aquifer
system.
Alleviating water shortage is an area of active
research; Yazdandoost et al. [14] suggested
lowering water consumption in arid regions as a
more sustainable approach than
seawater conveyance. However, due to the high
water demand, this option is not feasible. Instead,
desalination of seawater is often proposed as a
practical solution; Greenbaum [15] explained how
the growing demand for water in the south Levant
region could be met by seawater desalination as well
as water recycling for agriculture. In Jordan,
desalination can be done using seawater from GoA,
which is the only seaport in the country. Therefore,
many researchers were interested in the environment
at GoA; Al-Taani et al. [16] investigated marine
ecosystem and water quality at GoA. Al Hseinat et
al. [17] evaluated the role of zero discharge policy at
GoA in improving environmental conditions. Al-
Absi et al. [18] investigated the levels of 16 trace
and heavy elements in seawater in the northern Gulf
of Aqaba.
In Jordan, many water projects have been
proposed, especially the idea of conveying seawater
from GoA; this was planned in the Red Sea-Dead
Sea conveyance (RSDSC) project [19]. Quba'a et al.
[20] studied alternatives to increase water supply in
Jordan River Basin including the Red Sea–Dead Sea
Conveyance and pipeline from Turkey. Al-Maabreh
et al. [21] tested scale mitigation in Disi-Amman
water pipeline using nanofiltration and chemical
addition. Akash et al. [22] proposed hydropower
desalination system using energy generated by
flowing water from Disi to Aqaba [23]. However,
despite being a sound proposal, this idea relies on
transporting fossil water, which is non-renewable;
therefore, the proposal is unsustainable. The
potential for laying a straight pipeline from the Red
Sea to Jafer Basin in order to create an artificial lake
was investigated by Al-Habahbeh [24]; however,
this work proposes a more feasible solution, which
is to construct a minimum gradient pipeline for
water conveyance. Furthermore, the potential for
excavating a descending tunnel to flow water by
gravity from the Red Sea to Jafer Basin in order to
create a sustainable lake was proposed by Al-
Habahbeh [25]; however, the current proposal is
much more affordable.
Among the benefits of artificial lake
development is the flourishing agriculture. Holguin
et al. [26] reviewed the potential of growing saline
crops in desert areas for food and biofuel
production. AbuDalo et al. [27] assessed the
characteristics of an artificial lake containing a
mixture of treated wastewater and rainwater to
examine whether the nutrient loading is sufficient
for fish culture.
From the above discussions, it is clear that the
proposed artificial lake would solve two problems;
firstly, it will expand the available coastline by
multiple folds. Secondly, it will provide seawater
for possible desalination in a location closer to the
center of the country. The artificial lake design
process starts with formulating the problem as
shown in section 2. The problem solution is
presented in secion-3; it consists of the reservoir
design as well as water pumping and transporting.
The cost of the project is estimated in the economic
assessment section. Finally, a comparison between
the curved and the straight paths of the pipeline is
conducted.
2 Problem Formulation
The general plan of the RSJBC project is shown in
Fig. 1. It consists of two major components; the first
one is seawater transportation system, which
includes pipes and pumps, with the intake installed
at GoA (Point A) and the discharge installed at JB
(Point B). The length of the pipeline is 220 km. The
second component is the artificial lake that will be
developed inside JB (The blue region above Point
B). The proposed area of the Lake is 250 km2.
It is noted in Fig. 1 that the pipeline is not
straight, but rather curved towards the east side. The
reason for that is to avoid crossing the Shara
Mountains, which means climbing up to 1,350 m
above sea level (ASL). A schematic diagram for the
RSJBC project alignment is shown in Fig. 2, where
seawater is pumped from Red Sea (point 1), at sea
level to South eastern desert (point 2) at 894 m
ASL. From point 2, water will flow by gravity to JB
(point 3), at 850 m ASL, where the lake is formed.
There is a possibility for hydro-energy generation in
the downslope, which will be investigated.
For the water conveyance system, a pipeline is
selected. The water intake will be placed in GoA,
while multiple pumping stations will be deployed
along the pipeline. This arrangement will result in
steady pressure in the pipeline. The estimated total
length of the pipeline is 220 km. The pipeline course
has to go up and down following the terrains, and
having multiple pumps along the way would prevent
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
826
Volume 18, 2022
back flow. The RSJBC project is divided into two
phases; in phase-I, the pipeline and pumps are
constructed, while in phase-II, the basin is filled up
with water. After the completion of Phase-II, it will
be necessary to continue pumping a certain amount
of water in order to compensate for evaporated
water. In the meantime, an additional amount can be
pumped and desalinated in order to fulfill the
growing needs for fresh water in the area. The main
steps of the lake development algorithm are shown
in Fig. 3.
Fig. 1: RSJBC pipeline plan [28]
Fig. 2: Pipeline route around the mountains
3 Problem Solution
3.1 Reservoir Design
The proposed lake will be located in JB, which is a
unique natural place. It is a dry and quiet dish-like
area located in the south-eastern Jordanian desert,
about 60 km from Ma'an [29] and 6 km to the east
of Jafer town. It is a flat white basin which collects
rain
water from the surrounding mountains.
Furthermore, the floor of the basin is very hard and
do not grow any vegetation [30]. A schematic plan
of the basin is shown in Fig. 4, where the Lake is
designed to occupy the enclosed area, which equals
250 km2, while the perimeter equals 105 km. In
summer, this place is very dry, while in winter, fresh
water flowing from the surrounding mountains
accumulates in the basin. The annual direct rainfall
(RB) on the basin is given by:
(1)
Where RA is the annual rate of rainfall in the
basin, equal to 32 mm/year [32], and AB is the area
of the basin, equal to 250 km2. The resulting RB is 8
million cubic meters per year (MCM/y). The outer
JB has a circular shape with 100 km diameter and a
total area of 7,366 km2. JB is located inside the
outer basin. It has a mean elevation of 850 m ASL
[33], as shown in Fig. 4. JB region is characterized
as a hyper-arid zone [34]. The rate of flood flow
into the basin in a wet year is 15 MCM/y [35]. The
total water volume (Vw) needed to fill up the basin
can be calculated by multiplying the area by the
depth. The area of the basin (AB) is 250 km2, and the
average depth (DB) is 8 m [36]. Therefore, the
volume of the water (V) is calculated by:
(2)
Fig. 3: Lake development algorithm
Fig. 4: Layout of the proposed lake [31]
Seawater
pumping
Filling the
basin
Lake is full
Pumps
installation
Pipeline
construction
Sizing pipeline
and pumps
Calculate lake
volume
Set filling time
duration
Find seawater
flow rate
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
827
Volume 18, 2022
Equation (2) is used to calculate the water
volume needed to fill up the basin and create the
lake; the resulting volume is 2,000 MCM. The main
source of water used to fill up the lake is the
seawater pumped from GoA. The contribution of
fresh flood and rain water adds up to 23 MCM. It
was confirmed that after filling up the lake, the
nearby Jafer town and the airbase will still be 3 to
19 m above water level. In order to accurately
calculate the volume of seawater that must be
transported into the basin, due attention should be
paid to evaporation. The combination of high
temperatures and low humidity in the area results in
an extremely high evaporation rate. The evaporation
rate ranges between 1,600 mm/y in the northern
Highlands and 4000 mm/y in the south eastern
desert [37]. Assaf and Kessler [38] estimated an
annual evaporation rate of 280 W/m2 in GoA, which
is equivalent to 1 cm/day of evaporation. Therefore,
the expected evaporation rate from the lake (ER) can
be estimated using the above data as 3.83 m/y. The
volume of evaporated water is calculated by
multiplying ER with the water surface area (AB),
which yields an annual evaporation rate of 958
MCM from the surface of the lake. In addition, the
marginal amounts of falling rain (8 MCM/y) and
incoming seasonal streams (15 MCM/y) are
subtracted from the needed supply.
Seawater pumping requirements are assigned
based on the proposed lake capacity calculated
using eqn. (2), which equals 2,000 MCM. Pumping
capacity should be designed such that it can fill up
the basin in a reasonable time frame. It will be
assumed that the time needed to fill up the lake is
three years. This is considered a reasonable time for
a project of this size. During each of the first three
years of the project, 1,602 MCM must be pumped
into the Lake, as shown in Table 1. However,
starting from the fourth year, 935 MCM must be
pumped annually in order to compensate for
evaporation, and keep the water level constant. The
pumping capacity must be designed based on the
maximum required volume which is 1,602 MCM/y.
Based on this assumption, the design flow of
seawater (QSW) during the first three years is
calculated as:
 

󰇛
󰇜 (3)
However, in the fourth year and beyond, a rate of
30 m3/s must be continuously pumped to keep the
level of water constant. The required pumping
volumes are presented in Table 1. It is noted that the
water depth at the end of the first, second, and third
years is 2.7 m, 5.3 m and 8 m, respectively. An
important outcome of the RSJBC project is the
possibility of desalinating up to 21 m3/s of seawater
to fulfill the needs of the area. The 21 m3/s
represents the difference between the 51 m3/s used
for three years to fill up the lake, and the 30 m3/s
needed after that to keep the water level constant.
Assuming a recovery rate of 45%, the rate of
produced fresh water could reach 9.45 m3/s, which
amounts to 298 MCM/y.
Table 1. Basin filling plan
Description
(Volumes in
MCM)
1st
Year
2nd
Year
3rd
Year
4th
Year
Total
Operation
Water
volume of
the Lake
667
667
667
0
2,000
Add
Evaporation
from the
Lake
958
958
958
958
3,832
Add
Flooding
streams into
Lake
15
15
15
15
60
Subtract
Direct rain
into Lake
8
8
8
8
32
Subtract
Pumping
needed into
Lake
1,602
1,602
1,602
935
5,741
---
Net volume
in the Lake
667
1,333
2,000
2,000
---
---
Water depth
in the Lake
(m)
2.7
5.3
8.0
8.0
---
---
Pumping rate
into Lake
(m3/s)
51
51
51
30
---
---
3.2 Pumping and Transporting
The pumping rate will be designed based on the
required water flow rate given by eqn. (3). As for
conveyance, rigid or flexible pipes must be utilized.
Due to evaporation losses from the lake, it is
expected that pumping will be permanent; therefore,
the quality and reliability of the selected pipes and
pumps should be good enough to endure long life
cycles. The pipeline design includes several
parameters, such as Length, Diameter, Thickness,
and Material. Multiple values of the pipe diameter
will be investigated; from 2-7 m. A pipe diameter of
1 m is not considered in this work because the
pressure will be too high. The wall thickness of the
pipe is calculated using the following equation [11]:

 (4)
Where, p is Water pressure, Dpipe is Pipe
diameter, is Wall safety tensile stress, and δ is
Pipe wall thickness. The effect of material safety
tensile stress on pipe wall thickness for pipe
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
828
Volume 18, 2022
diameter of 3 m and pressure of 5 atm was checked
to be safe. Considering pipe material selection, there
are different options available; such as steel, plastic,
fabric and composite. The mean water velocity in a
pipe of diameter Dpipe is equal to volumetric flow
rate divided by the pipe cross-sectional area, defined
as:
 

(5)
Where the seawater flow rate through the pipe is
QSW. The transport system includes a series of
pumps where their main parameter is the pumping
power Pp, which can be obtained from the grid. The
power required to impel the water within the pipe is
given by:
 (6)
Where g is the gravitational acceleration (= 9.81
m/s2), ρSW is the density of seawater (= 1,030
kg/m3), H is the hydraulic head and ηp is the
efficiency of the pump (= 0.75). The hydraulic head
is obtained by adding the maximum elevation of the
pipe above sea level Hpipe (= 894 m), as shown in
Fig. 2, to the lost pressure height H) due to
friction, which equals:
 (7)
In this work, only linear pressure losses will be
considered, and the lost pressure height will be:


 (8)
Where Lpipe is the pipe length and λ is the coefficient
of linear pressure loss, given by:
󰇱



 (9)
The expression for Reynolds number is given by:

 (10)
Where vsw is the kinematic viscosity of seawater
(=13×10-4/ρsw) m2/s.
Pump specific power for a 1 m3/s flow rate is given
by:
 
 
(11)
A clear conclusion is that using a large diameter
pipe combined with low pressure is much more
energy efficient. The energy consumed with
pumping Epump,year (J/year) is obtained from:
 (12)
For analytical reasons, the pipeline route is
divided into two sections, the first section measures
two-thirds of the total length and extends from GoA
to South eastern desert. It is designated as Stage-I.
The second section measures one-third of the total
length and continues from the South eastern desert
to JB. It is designated as Stage-II. The basic
parameters of Stage-I of the pipeline are shown in
Table 2 for Year-1. Similarly, parameters for Stage-
II of the pipeline are presented in Table 3 for Year-
1. While pipeline results for different diameters and
water speeds for Year-1 (Stage I & II) are presented
in Table 4. After the 3 years needed to fill up the
basin, pipeline results for Year-4 (Stage I & II) are
shown in Table 5. It is noted that the data for the
second and third years are identical to the first year.
Considering the fourth year and beyond, the water
flow rate will be lower, as shown in Table 5.
Furthermore, if a diameter of 5 meters is used, it is
possible to generate energy during Stage-II, which is
a downslope. This fact is exploited in the
calculations, and it will for sure reduce the power
withdrawn from the grid.
The pumping flow speed as a function of pipe
diameter is shown in Fig. 5. Furthermore, since the
water flow rate needed after three years is less than
the flow required during the first three years, it is
reflected on the flow velocity as shown in Fig. 5.
The effect of pipe diameter on pumping power is
shown in Fig. 6. It is clear that employing a pipe
diameter of more than 3 meters would greatly
reduce the required pumping power. The same trend
is noted in Fig. 9, where the annual pumping energy
is plotted against the pipe diameter.
Table 2. Pipeline parameters, Year-1, Stage-I
QSW (m3/s)
51
Total pipe length
(km)
220
Start elevation (m)
0
End elevation (m)
894
Hpipe (m)
+894
Start location
Aqaba
End location
South eastern desert
Lpipe (m)
1.47×105
ρsw (kg/m3)
1,030
vsw (m2/s)
1.26×10-6
Δp (atm)
3
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
829
Volume 18, 2022
4 Economic Assessment
Due to their huge expenditure, it is essential to
calculate the cost of macro-engineering projects. For
the RSJBC project, each macro-engineered
component such as pipes and pumps involves two
associated costs; erection and operation. The
erection
cost is proportional to the quantity of each
component. This cost refers to pipeline and pumping
system construction, while the operation cost is
proportional to the volume of pumped water, after
installing the pipeline and pumps. In addition to the
total length, the pipeline cost depends on its
diameter and material, where the cost of pipe
installation depends mainly on the diameter. In this
section, the cost of the pipeline and the pumps
enabling steady water shifting is calculated. The
cost cpipe of the conducting pipe is determined by
[11]:
 (13)
Where cpipe,1 is the cost of a unit length of the pipe.
Table 3. Pipeline parameters, Year-1, Stage-II
QSW (m3/s)
51
Total pipe length
(km)
220
Start elevation (m)
894
End elevation (m)
858
Hpipe (m)
-36
Start location
South eastern desert
End location
Jafer basin
Lpipe (m)
7.33×104
ρsw (kg/m3)
1,030
vsw (m2/s)
1.26×10-6
Table 4. Pipeline results, Year-1 (Stage I & II)
Dpipe
(m)
wSW
(m/s)
ΔH
(m)
Hydraulic
Head (H)
(m)
Ppump
(MW)
Number
of
stations
Δp
(atm)
Ppump/
Station
(MW)
2
16
7,130
10,335
5,522
326
3
24
3
7
1,468
2,243
1,626
63
3
24
4
4
315
1,179
854
36
3
24
5
3
129
1,003
692
29
0.3
24
Table 5. Pipeline results, Year-4 (Stage I & II)
Dpipe
(m)
wSW
(m/s)
ΔH
(m)
Hydraulic
Head (H)
(m)
Ppump
(MW)
Number
of
stations
Ppump/
Station
(MW)
2
9
2,465
3,359
1,842
130
14
3
4
343
1,237
554
36
14
4
2
85
979
394
28
14
5
2
29
923
359
27
14
Fig. 5: Flow velocity vs. pipe diameter
Fig. 6: Pumping power vs. pipe diameter
Similarly, the cost of pipe installation, cinst,pipe is
given by:
  (14)
Where cinst,pipe,1 is the cost of installing one unit
length of the pipe. The unitary cost depends on
different factors, such as pipe diameter Dpipe and
material. The cost of pump mounting, Cpump, is
determined by:
 (15)
Where cpump,1 is the cost of the pump unit power.
In order to transform JB into a lake, a number of
pumps must be installed along the pipeline as
indicated in Tables 4 and 5. The first part of the
water transport system (Stage-I) transmits the water
to point 2 in Fig. 2, at an elevation of 894 m ASL.
This point is located 147 km from GoA and 73 km
from JB. After passing point 2 on the way to Jafer,
the pipeline descends down from 984 m to 850 m,
with 34 m water column. However, according to
analysis, hydropower could be generated only after
three years using a 5 m pipe diameter. Considering
the cost of an average quality pump of unit power
cpump,1 as 800 $/kW [11], the cost of energy
consumed during one year, cyear is calculated as [12]:
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
830
Volume 18, 2022
 (16)
Where cyear,1 = 0.1$ k/Wh. For N years, the energy
cost, c, is given by:
 (17)
Where N is the number of service years. The
initial investment cost cinvest for the pipes and
pumping installations is given by:
 (18)
After constructing the pipeline and pumping
stations, it will take three years of pumping to fill up
the basin. During that period, annual pumping cost
will be constant. However, after filling up the lake,
the pumping cost will decrease and stay constant.
An estimation of the investment costs is presented in
Tables 6 to 12; Table 6 depicts the annual operating
cost for the SP pipeline for multiple diameters.
Table 7 shows the pipeline cost of Stage-1 during
the first year. Table 8 provides the pumping cost
during the second year for both Stage-I and Stage-II.
Table 9 shows the pumping cost during the fourth
year for both stages. Table 10 depicts the sum of the
initial cost and the pumping cost for steel pipes. The
annual operating cost for CP pipeline for multiple
diameters is shown in Table 11.
In order to decrease the cost of pumping,
floating PV cells could be deployed on the surface
of the Lake. Ikhennicheu et al. [39] presented three
cases of floating solar PV farms, small, large and
offshore. Furthermore, renewable resources had
been proposed by Salem and Hudaib [40] to pump
water via pipeline and excavated tunnel into Qattara
Depression Reservoir. The cost of pipeline made of
different materials versus pipe diameter is shown in
Fig. 7. The highest is the steel and the lowest is the
fabric. Fig. 8 shows the pumping cost for different
pipe diameters. It is noted that energy and
consequently cost decreases with pipe diameter,
where there is a turning point at 4 meters diameter.
The annual pumping energy for different pipe
diameters is shown in Fig. 9. The energy decreases
sharply from 2 m to 3 m diameter. The pumping
cost variation with pipe diameter is plotted in Fig.
10. It is noted that the cost decrease tangibly after 4
m diameter.
From the previous results, it is noted that if
fabric pipes are deployed, the development cost of
the RSJBC project can be minimized. Within this
option of pipe material, the minimum cost can be
achieved using a 6 m diameter, which equals 2.74
B$. On the other hand, the total annual operating
cost is equal to 306 M$.
Table 6. Annual operating cost (SP)
Table 7. Cost of pipeline, Year-1, Stage-I
Dpipe
(m)
Pumps
(M$)
Pump
Energy
(M$)
Steel
pipe &
pump
(B$)
Plastic
pipe &
pump
(B$)
Fabric
pipe &
pump
(B$)
2
4,227
4,628
9,32
9.18
8.98
3
1,010
1,106
2,82
2.61
2.32
4
623
678
2,23
1.95
1.56
5
535
585
2,29
1.94
1.45
Table 8. Cost of pumping, Year-2 (Stage I & II)
Dpipe (m)
Pumping Energy (M$)
2
6,651
3
1,368
4
726
5
587
Table 9. Cost of pumping, Year-4 (Stage I & II)
Dpipe (m)
Pumping Energy (M$)
2
1,594
3
481
4
345
5
315
Fig. 7: Cost of pipeline vs. diameter
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
831
Volume 18, 2022
Fig. 8: Pumping cost vs. pipe diameter
Fig. 9: Annual pumping energy vs. pipe diameter
Fig. 10: Pumping cost vs. pipe diameter
Table 10. Initial & pumping costs for Steel pipes
Dpip
e
(m)
Pump
s &
pipes
(B$)
Pumpin
g
Energy
Y-1 (B$)
Pumping
Energy
Y-2 (B$)
Pumpin
g
Energy
Y-3 (B$)
Total
developmen
t (B$)
3
2.28
1.36
1.36
1.36
6.35
4
2.06
0.72
0.72
0.72
4.22
5
2.29
0.58
0.58
0.58
4.04
6
2.59
0.55
0.55
0.55
4.24
Table 11. Annual operating cost for CP
Dpipe (m)
Cost of pumping (M$)
3
480
4
345
5
315
6
306
7
303
5 Comparison between Curved Path
(CP) and Straight Path (SP)
This section compares between two pipeline routes;
the first route is the one described in this work and
shown in Fig. 1. Because of its shape, it is called;
"Curved Path (CP)". The second route connects
points A and B in Fig. 1 by a straight line. This
alternative route is called; "Straight Path (SP)".
However, due to the en-route Mountains, this
pipeline has to climb 1,350 m ASL, and then
descend to 858 m ASL at point B in Fig. 1. Using
the SP, the lowest total development cost of the
RSJBC project can be obtained using fabric pipe.
Within this pipe material option, a diameter of 6 m
provides the minimum cost, standing at 3.01 B$, as
opposed to 2.74 B$ for the CP. The corresponding
annual operating cost is equal to 304 M$, versus 306
M$ for the CP. This means the CP provides the
minimum possible development cost for the RSJBC
project, even though the operating cost is slightly
higher than SP. The total cost for different pipe
diameters is shown in Fig. 11 for CP and SP. While
the annual operating cost for different pipe
diameters is shown in Fig. 12. The full comparison
between CP and SP is shown in Table 12; it is noted
that the pipe diameter has a large influence on the
cost; for large diameters, CP is better than SP in
terms of development cost and annual operating
cost. The cost timeline for SP and CP both using
Fabric pipe is shown in Fig. 13. One more point to
consider is that CP extends through vacant desert,
while SP extends over the mountains, where there
are more human activities, which create more
obstacles to the pipeline route.
Fig. 11: Total cost vs. pipe diameter
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
832
Volume 18, 2022
Fig. 12: Annual operating cost
Fig. 13: Cost timeline for SP & CP (Fabric pipe)
Table 12. Annual operating cost for CP & SP
6 Conclusion
This work presents a design of an innovative macro-
engineering project; the proposed project is called
RSJBC and involves a seawater pipeline extending
from GoA to JB, where an artificial Lake is created.
After the construction of the pipeline and the
pumping stations is completed, and the project is
commissioned, it will take three years to fill-up the
basin. Once the Lake is filled-up, the pumping rate
delivered to the Lake must be reduced from 51 m3/s
to 30 m3/s, to keep the water level constant. The
surplus flow of 21 m3/s can be desalinated to fulfill
the needs of the area. Assuming a recovery rate of
45%, the rate of produced fresh water could reach
9.45 m3/s, which equals 298 MCM/y. The suggested
pipeline route (CP) is curved so as to avoid high
altitude mountains if it were to go straight (SP).
However, to confirm the benefit of this approach, a
comparison is conducted between CP and SP. It was
revealed that using CP, the lowest development cost
of RSJBC project can be realized, provided fabric
pipe is selected. Specifically, a pipe diameter of 6 m
provides a minimum development cost of 2.74 B$,
with corresponding annual operating cost of 306
M$. There is a small difference between the
operating costs for both designs, which can be
neglected.
Furthermore, attention should be paid to the fact
that CP extends through vacant desert while SP
extends over the mountains where there is more
human activity going on, which creates more
obstacles to the pipeline route.
Since the floor of the basin is completely flat,
once it is covered with water, the lake will have
constant water depth. In this work, the main concern
is the relatively high operating cost, which is due to
evaporation process. Since evaporation rate is much
higher than recharge rate, the salinity level of the
lake is expected to rise. However, evaporation rate
will decrease with increasing salinity. Future
research is recommended on the ecological effects
and sustainability of the lake; especially the salinity
increase rate and the feasibility of mining and using
the excess salt. On the cost aspect, one possible way
to reduce the operating cost is to schedule pumping
during grid off-peak hours. Another option is to
invest in solar photovoltaic (PV) energy to power
the continuous pumping needed. The PV modules
can be conveniently positioned on the surface of the
lake. In this case, the efficiency of the modules will
be improved by the cooling provided by seawater.
References:
[1] Megdiche-Kharrat F., Zheng X. Y., Moussa
M., Famin Z., Angelakis A. N., Historic
hydraulic works: paradigms of traditional good
water governance, integrity and sustainability,
Water Science and Technology: Water Supply,
Vol.20, No.7, 2020, pp. 2484-2498.
https://doi.org/10.2166/ws.2020.146.
[2] Al-Saqarat B. S., Abbas M., Lai Z., Gong S.,
Alkuisi M. M., Abu Hamad A. M. B., Carling
P. A., Jansen J. D., A wetland oasis at Wadi
Gharandal spanning 125-70 ka on the human
migration trail in southern Jordan, Quaternary
Research (United States), Vol.100, 2021, pp.
154-169. https://doi.org/10.1017/qua.2020.82.
[3] Roje-Bonacci T., Splitu S., Građevinarstva F.,
Geodezije A., The impact of hydrotechnical
Dpipe
(m)
CP
SP
Development
cost
(B$)
Annual
operating
cost (B$)
Development
cost
(B$)
Annual
operatin
g cost
(B$)
3
5.60
0.48
4.4
0.42
4
3.22
0.34
3.2
0.33
5
2.79
0.32
3.02
0.31
6
2.74
0.306
3.01
0.304
7
2.77
0.30
3.05
0.302
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
833
Volume 18, 2022
interventions on the water regime of Baćina
Lakes, Hrvatske Vode, Vol.28, No.114, 2020,
pp. 277–290. https://hrcak.srce.hr/254511.
[4] Goodwin I. D., Roberts J. L., Etheridge D. M.,
Hellstrom J., Moy A. D., Ribo M., Smith A.
M., Modern to Glacial age subglacial meltwater
drainage at Law Dome, coastal East Antarctica
from topography, sediments and jökulhlaup
observations, Geological Society Special
Publication, Vol.461, No.1, 2018, pp. 215–230.
https://doi.org/10.1144/SP461.16.
[5] Lukman, Hidayat H., Subehi L., Dina R.,
Mayasari N., Melati I., Sudriani Y., Loads of
Pollution to Lake Toba and Their Impacts,
International Journal on Advanced Science,
Engineering and Information Technology,
Vol.11, No.3, 2021, pp. 930-936.
https://doi.org/10.18517/ijaseit.11.3.12733.
[6] Abd Aziz N., Toriman M. E., Gasim M. B.,
Muftah S., Barggig A., Kamarudin M. K.,
Water Quality Deterioration in Artificial Lake:
Their Impact and Sources, International
Journal on Advanced Science, Engineering and
Informat-ion Technology, Vol.7, No.1, 2017,
pp. 49- 56.
https://doi.org/10.18517/ijaseit.7.1.1012.
[7] Gupta J., Van der Zaag P., Interbasin water
transfers and integrated water resources
management: Where engineering, science and
politics interlock, Physics and Chemistry of the
Earth, Parts A/B/C, Vol.33, No.1–2, 2008, pp.
28-40.
[8] Mohanty R., Mohapatra A., Mohanty S.,
Assessment of the impacts of a new artificial
lake mouth on the hydrobiology and fisheries
of Chilika Lake, India, Lakes and Reservoirs:
Science, policy and management for
sustainable use, 2009.
https://doi.org/10.1111/j.1440-1770.
2009.00406.x.
[9] Badescu V. and Cathcart, R.B., Aral Sea partial
restoration. II. Simulation of time-dependent
processes, Int. J. Environment and Waste
Management, Vol.7, Nos.1/2, 2011, pp. 164-
174.
[10] Stone R., After revival, Iran's great salt lake
faces peril, Science, Vol.372, No.6541, 2021,
pp. 444-445.
https://doi.org/10.1126/science.372.6541.444.
[11] Badescu V., Cathcart R. B., Paulescu M.,
Gravila P., and Bolonkin A. A., Chapter 89
Geo-Engineering South Australia: The Case of
Lake Eyre, Macro-Engineering Lake Eyre with
imported Seawater. In: Badescu V., Cathcart R.
B., (eds) Macro-Engineering seawater in
unique environments. Environmental science
and Engineering (Environmental Engineering),
Springer, Berlin, Heidelberg, 2010.
https://doi.org/10.1007/978-90-481-9920-4_89.
[12] Badescu V., Cathcart R. B. and Bolonkin A.
A., Sand dune fixation: a solar-powered Sahara
seawater pipeline macro project, Land Degrad.
Develop., 2008. https://doi.org/10.1002/ldr.864.
[13] Gomaa S. M., Hassan T. M., Helal E.,
Assessm-ent of seawater intrusion under
different pump-ing scenarios in Moghra
aquifer, Egypt, Science of the Total
Environment, Vol.781, 2021. https://
doi.org/10.1016/j.scitotenv.2021.146710.
[14] Yazdandoost F., Noruzi M. M., Yazdani S. A.,
Sustainability assessment approaches based on
water-energy Nexus: Fictions and nonfictions
about non-conventional water resources,
Science of the Total Environment, Vol.758,
2021. https://doi.org/10.1016/j.scitotenv.2020.
143703.
[15] Greenbaum N., Hydrology and water
management in Israel and the southern Levant,
Geographische Rundschau, Vol.72, No.12,
2020, pp. 24–29.
[16] Al-Taani A. A., Rashdan M., Nazzal Y.,
Howari F., Iqbal J., Al-Rawabdeh A., Al Bsoul
A., Khashashneh S., Evaluation of the gulf of
Aqaba coastal water, Jordan, Water
(Switzerland), Vol.12, No.8, 2020.
https://doi.org/10.3390/w12082125.
[17] Al Hseinat M., Rasheed M., Al-Rousan S.,
Long-term quality record (1996–2018) of
coastal sediments at the complex industrial site
along the Jordanian coast of the Gulf of Aqaba,
Environmental Monitoring and Assessment,
Vol.192, No.443, 2020.
https://doi.org/10.1007/s10661-020-08390-3.
[18] Al-Absi E., Manasrah R., Abukashabeh A.,
Wahsha M., Assessment of heavy metal
pollutants at various sites along the Jordanian
coastline of the Gulf of Aqaba, Red Sea,
International Journal of Environmental
Analytical Chemistry, Vol.99, No.8, 2019, pp.
726-740.
https://doi.org/10.1080/03067319.2019.160945
9.
[19] Beyth M., The Red Sea and the Mediterranean–
Dead Sea canal project, Desalination, Vol.214,
2007, pp. 364–370.
[20] Quba'a R., El-Fadel M., Abou Najm M.,
Alameddine I., Comparative assessment of
joint water development initiatives in the
Jordan River Basin, International Journal of
River Basin Management, Vol.15, No.1, 2017,
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
834
Volume 18, 2022
pp. 115-131. https://doi.org/10.1080/15715124.
2016.1213272.
[21] Al-Maabreh A. M., Al-Rawajfeh A. E.,
Alshamaileh E., Al-Bazedi G. A., Mitigation of
scale problem in the pumped Disi water to
Amman, Jordan, Environment Protection
Engineering, Vol.45, No.1, 2019, pp. 97–110.
https://doi.org/10.5277/epe190108.
[22] Akash B. A., Al-Jayyousi O. R., Mohsen M. S.,
Multi-criteria analysis of non-conventional
energy technologies for water desalination in
Jordan, Desalination, Vol.114, 1997, pp. 1-12.
[23] Mohsen M. S., Water strategies and potential of
desalination in Jordan, Desalination, Vol.203,
2007, pp. 27–46.
[24] Al-Habahbeh O. M., Exploiting regional
topography and macro-engineering to
transform southeastern Jordanian desert into a
coastal area, Journal of Mechanical
Engineering Research and Developments,
Vol.44, No.10, 2021, pp. 251-265.
[25] Al-Habahbeh O. M., Sustainable design of an
artificial lake in Jafer basin based on gravity
flow, Mathematical Modelling of Engineering
Problems, Vol.9, No.1, 2022, pp. 101-110.
[26] Holguin Pena R.J., Medina Hernandez D.,
Ghasemi M., Rueda Puente E. O., Salt tolerant
plants as a valuable resource for sustainable
food production in arid and saline coastal
zones, Acta Biologica Colombiana, Vol.26,
No.1, 2021, pp. 116–126.
https://doi.org/10.15446/abc.v26n1.82412.
[27] AbuDalo M., El-khateeb M., Ayadi H., Al-
Rahahleh B., Jaradat A., Guermazi W., First
assessment of water quality of an
artificial lake for fish culture and irrigation: A
case study of water reuse in water shortage area
across the Middle East, Aquaculture Research,
Vol.52, No.3, 2021, pp. 1267–1281.
https://doi.org/10.1111/are.14985.
[28] Royal Jordanian Geographic Center, 2020.
http://rjgc.gov.jo/rjgc_site.
[29] Al-Rai Newspaper, 2016.
http://alrai.com/article/1032053.
[30] Ad-Dustour Newspaper.
https://www.addustour.com/articles/143047.
[31] Google maps:
https://www.google.jo/maps/@32.0151601,35.
8607108,15z?hl=en.
[32] Kumar A. and Mozar S., 500th Volume of
LNEE, ICCCE 2018, Proceedings of the
International Conference on Communications
and Cyber Physical Engineering, Springer,
2018.
[33] Aljazy A. D. and Al-Nasrat M. I., The History
of Al-Jafer in Southern Jordan from the Earliest
Times to the Establishment of Bedouin
Settlement Project (500,000 BC to 1962 AD),
Jordan Journal for History and Archaeology
(JJHA), 2017.
[34] Alzghoul M. and Al-husban Y., Topographic
Characteristics and Estimation of the Quantity
of Water Harvesting in Al-Jafer Depression,
JKAU/Arts and Humanities, Vol.28, 2020, pp.
455-473. https://doi.org/10.4197/Art.28-2.18.
[35] Al Kuisi M. and El-Naqa A., GIS based Spatial
Groundwater Recharge estimation in the Jafr
basin, Jordan Application of WetSpass
models for arid regions, Revista Mexicana de
Ciencias Geológicas, Vol.30, No.1, 2013, pp.
96-109.
[36] Vivid Planet Software GmbH,
Salzburg/Austria, 2022.
https://www.mapcoordinates.net/en.
[37] Water Resources Management Division,
Department of Environment and Conservation,
Government of Newfoundland and Labrador,
Water Resources in Jordan: A Primer, 2010.
[38] Assaf G. and Kessler J., Climate and Energy
Exchange in the Gulf of Aqaba (Eilat), Monthly
Weather Review, Vol.104, No.4, 1976, pp.
381–385.
[39] Ikhennicheu M., Danglade B., Pascal R.,
Arramounet V., Trebaol Q., Gorintin F.,
Analytical method for loads determination on
floating solar farms in three typical environ-
ments, Solar Energy, Vol.219, 2021, pp. 34-41.
https://doi.org/10.1016/j.solener.2020.11.078.
[40] Salem A. and Hudaib E., Evaluation of Al
Qattara Depression Renewable Energy Poten-
tials, WSEAS Transactions on Environment and
Development, Vol.10, Art. #47, 2014, pp. 444-
452.
Contribution of Individual Authors to the
Creation of a Scientific Article (Ghostwriting
Policy)
Osama Al-Habahbeh performed the design and
analysis.
Romil Al-Adwan performed the visualization.
Mustafa Al-Khawaldeh performed the validation.
Creative Commons Attribution License 4.0
(Attribution 4.0 International, CC BY 4.0)
This article is published under the terms of the
Creative Commons Attribution License 4.0
https://creativecommons.org/licenses/by/4.0/deed.en
_US
WSEAS TRANSACTIONS on ENVIRONMENT and DEVELOPMENT
DOI: 10.37394/232015.2022.18.77
Osama M. Al-Habahbeh,
Romil S. Al-Adwan, Mustafa A. Al-Khawaldeh
E-ISSN: 2224-3496
835
Volume 18, 2022