An Approach to Improve Power System Resiliency in Grid-Connected
Wind Turbine Generator Power System
KUNAL A. BHATT1, ASHESH M. SHAH2, VISHAL KUMAR GAUR3
1Department of Electrical Engg.,
L. D. College of Engineering,
Ahmedabad, Gujarat,
INDIA
2Department of Electrical Engg.,
Government Engg. College,
Bharuch, Gujarat,
INDIA
3Department of Electrical Engg.,
Motilal Nehru National Institute of Technology,
Allahabad, UP,
INDIA
Abstract: - A new concept of optimal Point-on-wave (PoW) switching to curtail the power system resiliency of
the wind power plant connected with a transformer is presented. Optimal PoW switching targets are determined
using mathematical analysis and tested on the simulation model. The said simulation model has been developed
using PSCAD/EMTDC software for system parameters of the existing wind power plant electrical network of
Gujarat, India. The proposed optimal PoW-based method is capable of reducing the magnetizing inrush current
exceptionally. Further, the proposed technique is also efficient in smoothening the voltage profile and
decreasing harmonic contents in the supply, which improves the power quality of the wind power plant
electrical network. Afterwards, to demonstrate the proposed technique based on optimal PoW, a hardware
model has been developed in a laboratory environment. The result of the hardware model provides a promising
outcome as proof of the proposed technique. In the end, a comparative evaluation with a recently developed
technique is also carried out where it has been observed that the proposed technique is providing superior
results.
Key-Words: - Point on the wave, Wind power, switching transients, Wind turbine to grid-connected
transformer, the magnetizing inrush of the transformer, harmonic contents in magnetizing
inrush.
Received: August 27, 2023. Revised: February 22, 2024. Accepted: March 19, 2024. Published: May 31, 2024.
1 Introduction
To minimize the level of greenhouse emissions and
other environmental problems, power engineers
around the globe are continuously improving
sustainable solutions to promote green energy, [1].
In this regard, solar, wind, and biomass power
plants have been found the most trustworthy
options to replace as a substitute for the fossil fuel-
based conventional energy sources, [2]. It is to be
noted that wind power plants have achieved huge
growth in the field of sustainable energy across the
world. Further, asynchronous Wind Turbine
Generators (WTG) have attained higher priority in
comparison with other peer generators in recent
decades due to exponential growth in power
electronic devices. [1], [3], [4],. However, the main
disadvantage of such types of WTGs is their poor
responses to voltage and frequency profiles during
switching and load variation, [5], [6].
Owing to uncertainty in the weather conditions,
the power generation of the wind plants varies by a
large amount. Subsequently, the penetration of the
wind power plant-based energy sources in the
conventional grid causes frequent switching
operations. These frequent switching operations
cause power quality issues at the distribution level
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
84
Volume 23, 2024
[1], [7], [8]. Thereafter, an approach to improve
power quality for wind-based distributed
generation systems using Lorentzian norm-based
adaptive filters has been discussed in [7]. However,
the selection of parameters for adaptive features is
very critical in this method. Though the above-
proposed methods have provided power quality
solutions, these methods have not brought out a
reliable solution in the case of magnetizing inrush
which has been produced during switching of
WTG.
Afterward, CIGRE working group carried out a
detailed study of power resiliency problems on
WTG considering the real-time system in the UK,
[9]. In the above discussion, it is to be observed
that WTG has been connected to a conventional
grid at an extra high voltage level using a step up
transformer. In this case, the transformer causes a
high magnetizing inrush current during
energization which is drawn from the WTG.
Subsequently, this event leads to the development
of a voltage dip in the distribution network which
may cause adverse effects on the equipment
working in the same network, [9]. Additionally, the
level of harmonic contents at the Point of Common
Coupling (PCC) in the distribution network also
increases owing to high inrush current, [10].
Moreover, the dc component of inrush current
further causes saturation in the instrument
transformer connected to the bus of the distribution
network, which may lead to the mal-functioning of
the protective system.
To minimize the level of inrush current (LIC)
during the energization of the transformer in the
grid-connected WTG network, PoW switching
techniques have been suggested in [11], [12], [13].
The application of PoW technique to minimize the
switching transient levels during the energization of
various power system equipment have also been
discussed in [14], [15], [16], [17]. Further, the
effect of operating time variation of circuit breaker
has been considered during the application of PoW
switching for energization of power system
components as explained in [18].
Brunke and his team members have presented
the application of a PoW strategy to mitigate the
inrush current during the energization of the power
transformer based on residual flux levels, [19],
[20]. Thereafter, Chandrasena et. al performed the
PoW switching technique for the energization of
the transformer on a real-time platform, [21].
However, the effect of statistical and systematic
variations of the circuit breaker is required to
minimize the inrush current in above proposed
techniques. In [22] and [23], heuristic search-based
algorithms have been presented to mitigate the mal-
operation of the differential relay during the
energization of a transformer. Though these
algorithms offer high accuracy, the choice of
parameters is the key limitation of the heuristic-
based techniques and also increases the protection
cost for the distribution network. In the above
methods, the level of residual flux in the core,
resistances of the primary and secondary windings,
magnetizing characteristic of the iron core, and
switching instant of the source side voltage play a
vital role in deciding the amount of inrush current,
[24].
Owing to the low moment of inertia and low
level of short circuit current capacity compared to
conventional power stations, the wind farm has
been considered a weak source of power
generation, [24]. During random energization, a
wind farm to grid-connected transformer draws
high inrush current and subsequently, it develops
voltage dip and other power resiliency problems in
the distribution network. Further, the dc offset
component of the inrush current causes saturation
in the core of the instrument transformer, which
further leads to the development of mal-operation
in the protection system. Thus, to mitigate the
magnetizing inrush current in the wind power plant,
an application of PoW for the energization of Wind
Farm to a connected Transformer has been
discussed in this paper. Initially, the frequency of
supply has been determined using the zero-crossing
technique. Afterward, the first phase to be closed
has been decided based on the peak of the reference
phase for different types of transformer
configuration, which results in a reduction in inrush
current, voltage dip, and harmonic contents. Thus,
the proposed method indicates improvement of the
power resiliency problems in grid-connected wind
power system networks.
2 Effect of Random Energization of
the Transformer Connected with
WTG
A wind farm to grid-connected transformer draws
high inrush current during random energization. In
turn, it also produces voltage dip and other power
resiliency problems in the distribution network.
Further, the dc offset component of the inrush
current may also lead to saturation in the core of
the instrument transformer. Henceforth, to
determine the LIC, voltage dip harmonic contents
& dc offset, a simulation study in the
PSCAD/EMTDC software package has been
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
85
Volume 23, 2024
carried out and the results have been depicted in
Figure 1. Figure 1(a), (b) and (c) show the LIC,
voltage dip and fundamental, harmonic & dc
contents respectively. It is to be noted that the first
phase has been switched on at zero crossing instant
and the remaining two phases after 5 ms. Further,
the short circuit capacity of the source has been
considered as 5 kA for WTG during the simulation
study.
It has been observed from Figure 1(a) and (b)
that the LIC and voltage dip during the energization
have been found as 2.89 pu and 0.827 pu,
respectively. Further, Figure 1 (c) shows the level
of fundamental component (I1), 2nd to 7th harmonic
contents (Ih2 to Ih7), and dc offset (Idc) of the
magnetizing inrush current of phase-c which attains
the highest level of inrush current in a simulation
study. It has been observed from Figure 1 (c) that
the levels of Ih2 and Idc attain high levels of
magnitude. Thus, from Figure 1, it has been
observed that LIC, harmonic components, and dc
offset lead to create voltage dip, power quality
issues, and power system resiliency problems in the
distribution network.
Fig. 1: Level of (a) inrush current, (b) voltage dip,
and (c) harmonics contents during energization of
wind to grid connected transformer
3 Optimal PoW-based switching
Techniques
To illustrate the Optimal PoW-based switching
technique for improving power system resiliency,
the network configuration, mathematical derivation
of PoW targets, and proposed techniques have been
described in the following sub-sections.
3.1 Network Configuration
The Single Line Diagram (SLD) of WTG
connected with the grid existing in Gujarat, India
has been shown in Figure 2. The whole system
illustrated in Figure 2 has been implemented in the
PSCAD/EMTDC software package. As shown in
Figure 2, the wind farm consists of ten units of 1.5
MW each. Hence, the total generation offered by
the wind farm has been considered as 15 MW.
Further, the voltage generated by WTG is 0.4 kV
which is stepped up to 11 kV using transformer T1,
which is connected in Δ/Y configuration. Then, to
connect this wind farm to the grid, two other
transformers T2 (11/400 kV) and T3(11/230 kV)
are connected in parallel. The parameters of these
transformers have been mentioned in the Table 1. It
is to be noted that at any instant, only one of the
secondaries (either 400 kV or 230 kV) remained in
connection, and at any point in time, any
transformer (either T2 or T3) remained in the
circuit.
Fig. 2: Single line diagram of WTG existed in
Gujarat, India
3.2 Mathematical Derivation of PoW
Targets
To determine the PoW closing targets for the
energization of Wind Farm to Grid Connected
Transformer, a Resistance-Inductance (R-L) series
circuit connected with an ac source supply has been
considered. In this case, the supply voltage at any
instant is represented by eq. (1).
󰇛󰇜 󰇛󰇜
(1)
Where, is maximum voltage, is phasor
rotating frequency and is the energization
instant of the circuit.
In case of R-L series circuit, the power factor
angle (󰇜 of the circuit is determined by eq. (2)
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
86
Volume 23, 2024
  
(2)
When an R-L series circuit has been switched on, it
develops two components namely (i) steady-state
component and (ii) exponentially decaying
transient component as indicated in eq. (3).
(3)
It is to be noted from eq. (3) that the transient
turns to be zero when =. This indicates that
when the switching angle is becoming equal to the
power factor angle, the transient term attaints zero
magnitude. Hence, to minimize the level of the
switching transient, the switching instant is to be
determined from the power factor angle. In the case
of a transformer, the inductive reactance () of
the winding is very high in comparison to winding
resistance (R). Hence, power factor angle
becomes equal to π/2 as per eq. (2). Therefore, if
the switching instant has to be made equal to
π/2 (i.e. instant to attend the peak of reference
voltage), the magnitude of current becomes almost
equal to steady state current during switching on
the instant. This criterion has been utilized in the
proposed technique to mitigate the magnetizing
inrush for improving power system resiliency.
Table 1. Details of wind farm to grid-connected
transformer
Knee point voltage
1.1 pu
Magnetizing current
1% of rated current
3.3 Proposed Technique
Figure 3 shows a flowchart of the proposed
technique. Whenever a change-over command is
detected by the circuit breaker, the data regarding
the transformer connection is collected. To decide
the deliberated time delay by the PoW device for
the circuit breaker closing instant, it is essential to
find the zero-crossing instant of the reference
voltage (i.e. voltage of phase-a for three-phase
system in this paper). Finding the zero-crossing
instant is not only deciding the time delay for the
circuit breaker closing instant but it also benefits in
finding accurate frequency whose variation is
found continuously during power system operation.
Thus, the frequency has been found based on the
time lapse between two consecutive zero crossing
instants.
After finding the frequency and converting this
frequency into a timestamp, the deliberate time
delay between the first peak to be closed on phase –
a and the last zero crossing instant has been
calculated, [25]. Subsequently determining the
deliberate time delay, the PoW based closing
targets for different types of connection of the
transformers have been identified. Thereafter,
based on the type of transformer connection, the
PoW closing commands have been given to the
closing coils of the different phases of the circuit
breaker. As mentioned, firstly, phase–a has been
energized, and thereafter, the remaining two phases
have been switched on after 5 ms depending upon
the type of transformer connection.
Fig. 3: Flowchart of Proposed method
4 Results and Analysis
4.1 Simulation Results
To test the performance of the proposed technique,
a simulation study on SLD shown in Figure 2 has
been carried out using PSCAD/EMTDC software.
As shown in Figure 2, transformer T1 has been
energized by closing the circuit breaker CB1.
Before providing a closing command to coils of
CB1, the frequency of the supply has been
determined by using the zero-crossing technique.
Hence, based on the measured frequency, the time
delay between the first peak of phase a has been
found out. After the said time delay, the PoW
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
87
Volume 23, 2024
command to the circuit breaker CB1 has been given
for energization of Δ/Y connected transformer T1
on phase a. Further, the remaining two phases
(phase b and then phase c) have also been
energized as mentioned in the proposed method.
The obtained results of magnetizing inrush,
voltage, and harmonic contents have been depicted
in Figure 4. As shown in Figure 4 (a), the LIC has
been observed to be 0.025 pu which is quite less
than 2.89 pu which has been found during random
switching. Moreover, the voltage profile has also
been found to be 1 pu in all phases of the
transformer during energization compared to 0.827
pu in the case of random energization. Hence, the
voltage dip has been reduced in this case and power
system resiliency has been improved. Furthermore,
the fundamental, harmonic contents and dc
decaying has been also observed as indicated in
Figure 4 (c). As shown in Figure 4 (c), the
magnitude of all the mentioned quantities has been
reduced drastically using the proposed PoW
technique.
Fig. 4: Level of (a) inrush current, (b) voltage dip,
and (c) harmonics contents during energization of
wind to grid connected transformer using proposed
technique
4.2 Hardware Setup
A prototype to validate the proposed technique has
been developed in the laboratory and the obtained
result is shown in Figure 5. Figure 5(a) illustrates
the block diagram of the hardware setup. As shown
in Figure 5 (a), the current signal has been collected
and they are sent to the zero crossing detection
circuit. The said circuit consists of a combination
of a rectifier and optocoupler which rectifies the
input current signal and finds the interruption of
input current at zero crossing. This zero crossing is
sensed by Arduino and processed to calculate the
frequency. In Arduino, software coding has already
been executed for zero crossing detection,
calculation of frequency, determination of optimal
closing instant, and triggering signal to solid state
device using IDE open-source software in
computer system. Hence, after determining the
frequency of the supply accurately, the time taken
to reach the peak of voltage has been calculated
and the optimal switching instant has been found.
At this instant, Arduino provides trigger commands
to the solid state switch at the peak of the voltage
wave in the transformer.
Figure 5(b) illustrates the snapshot of the
hardware setup which shows the computer system,
zero crossing detector circuit, Arduino circuit, solid
state switching, transformer (which is to be
energized), and digital signal oscilloscope. On
receiving the triggering signal, the solid-state
device turns on and the transformer energizes. This
energized current signal has been captured in a
digital signal oscilloscope and is shown in Figure 5
(c). As depicted in Figure 5 (c), the LIC is found to
be 0.085 pu which indicates the satisfactorily low
value of inrush in comparison to random
energization of the transformer. The details about
apparatus used for hardware set up is shown in
Table 2.
Table 2. Details about hardware setup
Apparatus
Specifications
Transformer
1.5 KVA, 440/230 volts
Solid state device
Triac, BTA41, 600 volts
Microcontroller
Arduino controller
4.3 Comparative Analysis
The proposed method based on Optimal PoW-
based technique has been examined in connection
with other published research articles based on [10]
and the results are depicted in Table 3. It has been
noticed from Table 3 that LIC is relatively lower in
the proposed technique in comparison with
published articles for simulation as well as
hardware results. In addition, it is also observed
that the voltage profile has also been improved
satisfactorily during simulation. The same result
has also been achieved with hardware setup.
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
88
Volume 23, 2024
Fig. 5: Hardware setup: (a) Block diagram, (b) Snapshot of setup, and (c) LIC
Table 3. Comparative analysis of suggested
scheme with published research article, [10]
Sr.
No.
Nomenclature
Proposed
Technique
Published
research
article in [10]
Simulation Results
1
LIC (pu)
0.025
1.44
2
Voltage level
(pu)
1
0.993
Hardware Results
1
LIC (pu)
0.085
0.54
5 Conclusion
A new optimal PoW-based technique is presented
to improve the power system resiliency in the wind
power plant connected with the transformer.
Initially, optimal PoW instant has been found using
mathematical analysis. Afterwards, a simulation
model for the wind power plant electrical network
of Gujarat, India has been developed in the
PSCAD/EMTDC software package. During
simulation, the application of optimal PoW instant
is remarkably reducing magnetizing inrush,
improving voltage profile, and decreasing harmonic
contents of current. Further, the analysis of the
proposed technique has also been carried out with
the help of hardware setup in a laboratory
environment whose outcome exceptionally
increases the reliability of the proposed method. In
the end, a comparative analysis of the proposed
technique with the recently presented method
provides improved results. In the future, work will
be performed to develop an algorithm for carrying
out PoW switching using the Internet of Things and
Artificial Intelligence.
References:
[1] S. S. Murthy, B. Singh, and V. Sandeep, “A
Novel and Comprehensive Performance
Analysis of a Single-Phase Two-Winding
Self-Excited Induction Generator,” IEEE
Trans. Energy Convers., vol. 27, no. 1, pp.
117–127, Mar. 2012.
[2] J.-M. Chapallaz, J. Dos Ghali, P.
Eichenberger, and G. Fischer, Manual on
Induction Motors Used as Generators.
Wiesbaden: Vieweg+Teubner Verlag, 1992.
[3] D. P. S, L. M, and M. G., “Minimization of
the Cost of Energy of Wind Turbine through
Various Power Models,” Int. J. Appl. Math.
Comput. Sci. Syst. Eng., vol. 4, pp. 14–20,
Jun. 2022.
[4] S. Saroha and S. K. Aggarwal, “A Review
and Evaluation of Current Wind Power
Prediction Technologies,” Wseas Trans.
Power Syst., vol. 10, pp. 1–12, 2015.
[5] M. A. M. A. Moftah, G. E.-S. A. Taha, and
E.-N. A. Ibrahim, “Active power filter for
variable-speed wind turbine PMSG
interfaced to grid and non-linear load via
three phase matrix converter,” in 2016
Eighteenth International Middle East Power
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
89
Volume 23, 2024
Systems Conference (MEPCON), 2016, vol.
12, pp. 1013–1019.
[6] X.-P. Z. and M. S. C. Wu, “Wind power
generation variations and aggregation,”
CSEE J. Power Energy Syst., vol. 8, no. 1,
pp. 17–38, 2022.
[7] A. K. K. Giri, S. R. Arya, R. Maurya, and
B. C. Babu, “Power Quality Improvement in
Stand-Alone SEIG-Based Distributed
Generation System Using Lorentzian Norm
Adaptive Filter,” IEEE Trans. Ind. Appl.,
vol. 54, no. 5, pp. 5256–5266, Sep. 2018.
[8] A. Wondwossen, G. Temesgen, B. Belete,
M. Shegaw, P. Chandrasekar, and K.
Prasanna, “Failure Analysis of Distribution
Transformer and Proposing Proper Solution
to Mitigate the Faults -A Case Study of
Kombolcha City Dessie District Ethiopian
Electric Utility, Ethiopia,” WSEAS
Transactions on Power Systems, vol. 18, pp.
310–320, Dec. 2023,
https://doi.org/10.37394/232016.2023.18.32
[9] P. Ti and N. O. Tes, “Wind Farm
Transformer Inrush Studies,” in PSCAD
Application notes, 2020, pp. 0-1–02.
[10] K. A. Bhatt, B. R. Bhalja, and U. B. Parikh,
“Evaluation of controlled energisation of an
unloaded power transformer for minimising
the level of inrush current and transient
voltage distortion using PIR-CBs,” IET
Gener. Transm. Distrib., vol. 12, no. 11, pp.
2788–2798, Jun. 2018.
[11] CIGRE Working group C4.307,
“Transformer energization in Power
Systems : A Study Guide,” 2014.
[12] J. Hu, B. Bisewski, R. Sherry, M. Dalzell,
M. Zavahir, and C. Bartzsch, “Converter
Transformer Inrush Control Using Hybrid
Pre-insertion Resistors and Point-on-Wave
Switching in the New Zealand HVDC
System,” in CIGRE sessions, 2016, pp. 1–8.
[13] A. Kumar, R. Perveen, and U. Parikh,
“Controlled Switching of Power
Transformer and Shunt Reactors for
Minimization of Switching Transients: A
Review,” J. Inst. Eng. Ser. B, vol. 103, no.
3, pp. 1013–1024, Jun. 2022.
[14] CIGRE Task Force 13.00.1, “Controlled
switching A state of the art survey- part I.,”
Oct. 1995.
[15] CIGRE Task Force 13.00.1, “Controlled
switching A state of the art survey- part II,,
ELECTRA, 1996.,” Feb. 1996.
[16] CIGRE WG A3.35, “Present and Future of
Controlled Switching,” in CIGRE -IEC
colloquium, 2016, pp. 1–11.
[17] ABB substation automation products,
“Switchsync TM PWC600 Product Guide,”
Vesteras, Sweden, 2013.
[18] K. A. Bhatt and B. R. Bhalja, “An approach
for controlled energization/re-energization
of shunt compensated transmission lines,”
Int. J. Electr. Power Energy Syst., vol. 120,
no. November 2019, p. 105986, Sep. 2020.
[19] J. H. Brunke and K. J. Frohlich,
“Elimination of transformer inrush currents
by controlled switching. I. Theoretical
considerations,” IEEE Trans. Power Deliv.,
vol. 16, no. 2, pp. 276–280, Apr. 2001.
[20] J. H. Brunke and K. J. Frohlich,
“Elimination of transformer inrush currents
by controlled switching. II. Application and
performance considerations,” IEEE Trans.
Power Deliv., vol. 16, no. 2, pp. 281–285,
Apr. 2001.
[21] W. Chandrasena, D. Jacobson, and P.
Wang, “Controlled Switching of a 1200
MVA Transformer in Manitoba,” IEEE
Trans. Power Deliv., vol. 31, no. 5, pp.
2390–2400, Oct. 2016.
[22] Z. S. Almajali, “A Discrimination Method
Between Transformer Inrush and Fault
Current Based on Chromatic Monitoring,”
WSEAS Trans. POWER Syst., vol. 16, pp.
308–315, Dec. 2021.
[23] T. S. Sidhu and M. S. Sachdev, “Online
identification of magnetizing inrush and
internal faults in three-phase transformers,
IEEE Trans. Power Deliv., vol. 7, no. 4, pp.
1885–1891, 1992.
[24] Cigre Wg C4.307, Transformer
Energization in Power Systems : a Study
Guide, no. February. 2014.
[25] D. Goldsworthy, T. Roseburg, D.
Tziouvaras, and J. Pope, “Controlled
Switching of HVAC Circuit Breakers:
Application Examples and Benefits,” in
2008 61st Annual Conference for Protective
Relay Engineers, 2008, pp. 520–535.
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
90
Volume 23, 2024
Contribution of Individual Authors to the
Creation of a Scientific Article (Ghostwriting
Policy)
The authors equally contributed in the present
research, at all stages from the formulation of the
problem to the final findings and solution.
Sources of Funding for Research Presented in a
Scientific Article or Scientific Article Itself
No funding was received for conducting this study.
Conflict of Interest
The authors have no conflicts of interest to declare.
Creative Commons Attribution License 4.0
(Attribution 4.0 International, CC BY 4.0)
This article is published under the terms of the
Creative Commons Attribution License 4.0
https://creativecommons.org/licenses/by/4.0/deed.e
n_US
WSEAS TRANSACTIONS on CIRCUITS and SYSTEMS
DOI: 10.37394/23201.2024.23.8
Kunal A. Bhatt, Ashesh M. Shah, Vishal Kumar Gaur
E-ISSN: 2224-266X
91
Volume 23, 2024